Anila BESS is a 209.0 MW other interconnection project in Wilson, Texas with a current status of operational. It is proposed to connect at Tap of 345 kV Elm Creek (Bus# 5133) - San Miguel Gen (Bus# 5901) Transmission Line Ckt 1.

209.0 MWCapacity
OperationalStatus
WilsonMarket
OtherTechnology

Project facts

Canonical nameAnila BESS
Queue ID26INR0077
Statusoperational
Source statusSS Completed, FIS Completed, IA
MarketWilson
TechnologyOther
Capacity209.0 MW
StateTexas
CountyWilson
Point of interconnectionTap of 345 kV Elm Creek (Bus# 5133) - San Miguel Gen (Bus# 5901) Transmission Line Ckt 1
Requested (queue) date2023-02-20
Proposed in-service date
Operational date2028-09-30
Withdrawn date
DeveloperAlina Energy LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata