Antonio Road BESS (27INR0090)

Antonio Road BESS is a 155.5 MW battery interconnection project in Bastrop, Texas with a current status of withdrawn.

155.5 MWCapacity
WithdrawnStatus
BastropMarket
BatteryTechnology

Project facts

Canonical nameAntonio Road BESS
Queue ID27INR0090
Statuswithdrawn
Source status—
MarketBastrop
TechnologyBattery
Capacity155.5 MW
StateTexas
CountyBastrop
Point of interconnection—
Requested (queue) date—
Proposed in-service date—
Operational date—
Withdrawn date2026-08-04
Developer—
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-30developerTempus Power management LLC—low
2026-09-30poi_namePaige 138kV, bus 7308, connecting to the existing substation via adding a breaker—low
2026-09-30phaseSS Completed, FIS Started, No IA—low
2026-09-30operational_date2027-06-01—medium
2026-09-30withdrawn_date—2026-08-04high
2026-09-30statusoperationalwithdrawnhigh
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-30
Data last materially changed2026-09-30
Page data generated2026-11-26

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata