Apex Bethel CAES (15INR0013)
Apex Bethel CAES is a 324.0 MW other storage interconnection project with a current status of withdrawn. It is proposed to connect at tap 345kV 3380 Big Brown - 3133 Richland Chambers.
324.0 MWCapacity
WithdrawnStatus
ERCOTMarket
Other StorageTechnology
Project facts
| Canonical name | Apex Bethel CAES |
|---|---|
| Queue ID | 15INR0013 |
| Status | withdrawn |
| Source status | withdrawn |
| Market | ERCOT |
| Technology | Other Storage |
| Capacity | 324.0 MW |
| State | — |
| County | — |
| Point of interconnection | tap 345kV 3380 Big Brown - 3133 Richland Chambers |
| Requested (queue) date | 2011-11-16 |
| Proposed in-service date | 2020-11-27 |
| Operational date | — |
| Withdrawn date | 2018-09-07 |
| Developer | Apex CAES |
| Utility / transmission owner | ERCOT |
What changed
No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.
Explore related data
Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.