ERCOT Interconnection Queue

The Electric Reliability Council of Texas (ERCOT) manages the interconnection queue for roughly 90% of Texas's electric load on its islanded grid.

The interXdata canonical warehouse currently tracks 1,980 interconnection requests in the ERCOT footprint, representing 391,109 MW of requested capacity. Of these, 161 are active and 613 have reached commercial operation.

1,980Total projects
161Active
613Operational
1,158Withdrawn
48Suspended
26,192 MWActive capacity

Capacity by technology

TechnologyProjectsRequested capacity
Wind521112,301 MW
Solar58297,410 MW
Gas21467,713 MW
Battery27637,141 MW
Other28229,831 MW
Coal3719,323 MW
Nuclear612,399 MW
Solar+Battery4510,468 MW
Other Storage52,900 MW
Wind+Battery61,026 MW
Offshore Wind3450 MW
Oil3146 MW

Queue intake by request year

Request yearProjectsRequested capacity
2025455,316 MW
20248314,275 MW
202314421,498 MW
202211922,340 MW
202116127,248 MW
202013923,317 MW
201918331,745 MW
201812524,331 MW
20179916,792 MW
20166211,803 MW
2015529,255 MW
20147517,024 MW

Largest active projects

ProjectQueue IDTechnologyCapacityStatusLocation
Fierce River Solar27INR0221Solar+Battery895.7 MWactiveStarr, Texas
Pinnington Solar24INR0010Solar+Battery653.7 MWactiveJack, Texas
TOCE TX BESS 226INR0334Battery523.4 MWactiveWharton, Texas
Elmax Power Station23INR0345Gas518.8 MWactiveHarris, Texas
Catamount Storage28INR0097Battery515.4 MWactiveHarris, Texas
Bottom Grass Solar23INR0082Solar+Battery508.6 MWactiveColorado, Texas
Hollow Branch Creek Storage24INR0423Solar+Battery460.0 MWactiveLeon, Texas
NRG THW GT 345 (TEF)24INR0482Gas456.0 MWactiveHarris, Texas
TRIFECTA Gas26INR0183Gas453.0 MWactiveMidland, Texas
BRP Artemis BESS24INR0130Battery411.3 MWactiveGrimes, Texas
Wilson BESS28INR0285Battery409.7 MWactiveWilson, Texas
Iron Belt Energy Storage25INR0208Battery401.9 MWactiveBorden, Texas
Bottom Grass Solar II25INR0152Solar+Battery401.6 MWactiveColorado, Texas
Dorado Solar22INR0261Solar401.4 MWactiveCallahan, Texas
SCOTT CROSSING SOLAR SLF27INR0020Solar+Battery364.1 MWactiveHaskell, Texas
Fighting Jays Solar21INR0278Solar351.3 MWactiveFort Bend, Texas
Middlebrook Solar Limited Liability Company24INR0418Solar+Battery316.2 MWactiveNacogdoches, Texas
Hickerson Solar21INR0359Solar+Battery311.1 MWactiveBosque, Texas
Platinum Storage22INR0554Battery309.5 MWactiveFannin, Texas
Canyon Wind18INR0030Wind308.8 MWactiveScurry, Texas
Larkspur Energy Storage23INR0340Battery307.5 MWactiveUpton, Texas
Glory Bee Solar24INR0368Solar+Battery305.0 MWactiveErath, Texas
BRP Aras BESS23INR0272Battery303.6 MWactiveUpton, Texas
BRP Passu BESS23INR0139Battery301.8 MWactiveWilbarger, Texas
Jukebox Solar28INR0281Solar281.0 MWactiveFrio, Texas

Most active developers

Developer (canonical)ProjectsCapacity
Nextera397,736 MW
Invenergy3510,180 MW
Eon286,088 MW
Airtricity, Inc255,371 MW
FPL225,842 MW
Cypress Creek Renewables202,438 MW
EDF Renewables Development, Inc.196,221 MW
Horizon Energy LLC184,479 MW
RWE Solar Development, LLC173,031 MW
Duke Energy Florida, LLC162,290 MW
Hecate Energy154,879 MW
Recurrent Energy151,828 MW
Gamesa Energy USA151,940 MW
TXU Power1410,946 MW
HEN Infrastructure, LLC 114139 MW

Recent material changes

No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.

Explore related data

Methodology & sources

Counts aggregate current canonical project records whose market region is ERCOT. Status is normalized to a five-value vocabulary (active, operational, withdrawn, suspended, unknown). Capacity is the primary requested MW per project. Withdrawn and operational projects are retained as historical records.

Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Receive a weekly summary of new, withdrawn, and materially changed projects in ERCOT.

Start tracking with interXdata