Arlington Battery Energy Storage System is a 25.0 MW battery interconnection project in Snohomish, Washington with a current status of active.

25.0 MWCapacity
ActiveStatus
BPATMarket
BatteryTechnology

Project facts

Canonical nameArlington Battery Energy Storage System
Queue ID67669_ABESS
Statusactive
Source status(V) Under construction, more than 50 percent complete
MarketBPAT
TechnologyBattery
Capacity25.0 MW
StateWashington
CountySnohomish
Point of interconnection—
Requested (queue) date—
Proposed in-service date2026-10-01
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerPUD No 1 of Snohomish County - (WA)

What changed

ObservedFieldOld valueNew valueMateriality
2026-11-01proposed_online_date2026-09-012026-10-01medium
2026-08-02new_project—activehigh

Explore related data

Source last checked2026-11-01
Data last materially changed2026-11-01
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned). Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.