Snohomish County, Washington — Interconnection Projects

The interXdata warehouse tracks 26 interconnection projects in Snohomish, Washington, representing 1,730 MW of requested capacity.

26Total projects
5Active
15Operational
6Withdrawn
1,730 MWRequested capacity

Technology mix

TechnologyProjectsRequested capacity
Gas41,055 MW
Other10612 MW
Battery758 MW
Solar56 MW

Projects

ProjectQueue IDTechnologyCapacityStatusLocation
500MW SnohomishG19Gas500.0 MWwithdrawnSnohomish, Washington
West Queue Project 22 — Gas in Snohomish, Washington22Gas302.0 MWwithdrawnSnohomish, Washington
Getchell SubstationL0603Other300.0 MWactiveSnohomish, Washington
250MW SnohomishG18Gas250.0 MWwithdrawnSnohomish, Washington
Beverly Park ExpansionL0273Other178.0 MWwithdrawnSnohomish, Washington
H M Jackson7588_1Other47.5 MWoperationalSnohomish, Washington
H M Jackson7588_2Other47.5 MWoperationalSnohomish, Washington
WA Queue Project G0832 — Battery in Snohomish, WashingtonG0832Battery25.0 MWactiveSnohomish, Washington
Arlington Battery Energy Storage System67669_ABESSBattery25.0 MWactiveSnohomish, Washington
H M Jackson7588_4Other8.4 MWoperationalSnohomish, Washington
H M Jackson7588_3Other8.4 MWoperationalSnohomish, Washington
Young’s Creek Hydro ProjectG0370Other8.0 MWoperationalSnohomish, Washington
Youngs Creek Hydroelectric Project57763_1Other7.5 MWoperationalSnohomish, Washington
Darrington57969_GEN1Other4.5 MWoperationalSnohomish, Washington
MESA 2 Energy Storage ProjectG0506Battery3.0 MWoperationalSnohomish, Washington
Qualco ProjectG0659Gas3.0 MWoperationalSnohomish, Washington
Arlington MicrogridG0593Solar2.0 MWoperationalSnohomish, Washington
WA Queue Project G0481 — Battery in Snohomish, WashingtonG0481Battery2.0 MWoperationalSnohomish, Washington
Snohomish North Snohomish CountyL0399Other1.7 MWwithdrawnSnohomish, Washington
WA Queue Project G0836 — Solar in Snohomish, WashingtonG0836Solar1.0 MWwithdrawnSnohomish, Washington
Arlington Microgrid64446_AMGBBattery1.0 MWoperationalSnohomish, Washington
Hardeson Battery Storage ExpansionG0500Battery1.0 MWoperationalSnohomish, Washington
WA Queue Project G1091 — Solar in Snohomish, WashingtonG1091Solar1.0 MWactiveSnohomish, Washington
WA Queue Project G0943 — Solar in Snohomish, WashingtonG0943Solar1.0 MWactiveSnohomish, Washington
Hardeson Battery StorageG0484Battery1.0 MWoperationalSnohomish, Washington
Arlington Microgrid64446_AMGPVSolar0.5 MWoperationalSnohomish, Washington

Top developers

Developer (canonical)ProjectsCapacity
Public Utility District No. 1 of Cowlitz County9498 MW
FPL2750 MW

Explore related data

Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: bpa-oasis; U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.