Astoria 345kV (J2546)

Astoria 345kV is a 185.0 MW wind interconnection project in Deuel, South Dakota with a current status of withdrawn. It is proposed to connect at Astoria 345kV.

185.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameAstoria 345kV
Queue IDJ2546
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity185.0 MW
StateSouth Dakota
CountyDeuel
Point of interconnectionAstoria 345kV
Requested (queue) date2022-09-14
Proposed in-service date2027-10-01
Operational date2027-10-01
Withdrawn date2025-10-27
Developer
Utility / transmission ownerOtter Tail Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.