South Dakota Interconnection Projects
interXdata tracks 478 interconnection projects in South Dakota representing 82,822 MW of requested capacity. The dominant technology by capacity is Wind. The most active counties are Grant, Deuel, Brookings.
478Total projects
40Active
184Operational
254Withdrawn
82,822 MWRequested capacity
4,475 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 259 | 56,263 MW |
| Coal | 21 | 7,490 MW |
| Solar | 48 | 6,730 MW |
| Gas | 67 | 6,576 MW |
| Other | 62 | 3,553 MW |
| Battery | 13 | 2,176 MW |
| Diesel | 7 | 32 MW |
| Oil | 1 | 2 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Grant | 40 | 6,542 MW |
| Deuel | 31 | 6,245 MW |
| Brookings | 28 | 4,655 MW |
| Codington | 27 | 4,431 MW |
| Pennington | 26 | 1,833 MW |
| Brown | 22 | 1,985 MW |
| Beadle | 18 | 1,563 MW |
| Campbell | 16 | 4,057 MW |
| Buffalo | 14 | 2,858 MW |
| Hand | 13 | 9,201 MW |
| Hyde | 13 | 3,079 MW |
| Clark | 13 | 1,418 MW |
| Jerauld | 13 | 1,210 MW |
| Minnehaha | 11 | 1,702 MW |
| Hughes | 11 | 1,112 MW |
| Bon Homme | 10 | 1,615 MW |
| Charles Mix | 10 | 423 MW |
| Stanley | 9 | 1,243 MW |
| Meade | 9 | 1,155 MW |
| McPherson | 9 | 6,220 MW |
| Day | 8 | 1,168 MW |
| Roberts | 8 | 3,450 MW |
| Yankton | 8 | 562 MW |
| Clay | 6 | 1,425 MW |
| Butte | 5 | 495 MW |
| Lincoln | 4 | 527 MW |
| Turner | 4 | 525 MW |
| Todd | 4 | 291 MW |
| Mcpherson | 3 | 794 MW |
| Moody | 3 | 361 MW |
| Spink | 3 | 123 MW |
| Tripp | 3 | 450 MW |
| Haakon County | 3 | 800 MW |
| Walworth | 3 | 586 MW |
| Lawrence | 3 | 104 MW |
| Pennington County | 2 | 153 MW |
| McPherson County | 2 | 400 MW |
| Brule | 2 | 40 MW |
| Aurora | 2 | 40 MW |
| Grant County | 2 | 300 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Collins | T32 | Wind | 2,500.0 MW | withdrawn | McPherson, South Dakota |
| MISO Queue Project G705 — Wind in Hand, South Dakota | G705 | Wind | 2,000.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0612 — Wind in Hand, South Dakota | GI-0612 | Wind | 2,000.0 MW | withdrawn | Hand, South Dakota |
| West Queue Project GI-0609 — Wind in Buffalo, South Dakota | GI-0609 | Wind | 1,500.0 MW | withdrawn | Buffalo, South Dakota |
| West Queue Project GI-0611 — Wind in Hand, South Dakota | GI-0611 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project G704 — Wind in Hand, South Dakota | G704 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project G884 — Wind in Roberts, South Dakota | G884 | Wind | 1,500.0 MW | withdrawn | Roberts, South Dakota |
| MISO Queue Project G703 — Wind in Hand, South Dakota | G703 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| Collins III | T34 | Wind | 1,500.0 MW | withdrawn | McPherson, South Dakota |
| Astoria 345kV substation | J3941 | Gas | 1,144.0 MW | operational | Deuel, South Dakota |
| Collins II | T33 | Wind | 1,000.0 MW | withdrawn | McPherson, South Dakota |
| West Queue Project GI-0111a — Coal in Mcpherson, South Dakota | GI-0111a | Coal | 750.0 MW | withdrawn | Mcpherson, South Dakota |
| MISO Queue Project G731 — Wind in Jerauld, South Dakota | G731 | Wind | 750.0 MW | withdrawn | Jerauld, South Dakota |
| West Queue Project GI-0610 — Coal in Stanley, South Dakota | GI-0610 | Coal | 700.0 MW | withdrawn | Stanley, South Dakota |
| West Queue Project GI-0702 — Coal in Campbell, South Dakota | GI-0702 | Coal | 700.0 MW | withdrawn | Campbell, South Dakota |
| West Queue Project GI-0517 — Coal in Campbell, South Dakota | GI-0517 | Coal | 700.0 MW | withdrawn | Campbell, South Dakota |
| MISO Queue Project G118 — Other in Grant, South Dakota | G118 | Other | 650.0 MW | withdrawn | Grant, South Dakota |
| West Queue Project GI-0408 — Coal in Clay, South Dakota | GI-0408 | Coal | 600.0 MW | withdrawn | Clay, South Dakota |
| MISO Queue Project G392 — Coal in Grant, South Dakota | G392 | Coal | 600.0 MW | withdrawn | Grant, South Dakota |
| MISO Queue Project H095 — Wind in Roberts, South Dakota | H095 | Wind | 550.0 MW | withdrawn | Roberts, South Dakota |
| Chappelle Creek 345 kV Substation | GEN-2023-106 | Wind | 504.0 MW | withdrawn | Hyde, South Dakota |
| West Queue Project GI-0318 — Coal in Beadle, South Dakota | GI-0318 | Coal | 500.0 MW | withdrawn | Beadle, South Dakota |
| West Queue Project GI-1106 — Coal in Pennington, South Dakota | GI-1106 | Coal | 500.0 MW | withdrawn | Pennington, South Dakota |
| West Queue Project GI-0319 — Coal in Clay, South Dakota | GI-0319 | Coal | 500.0 MW | withdrawn | Clay, South Dakota |
| Split Rock - White (WAPA) 345.0kV | J3964 | Solar | 490.0 MW | operational | Brookings, South Dakota |
| BROOKINGS COUNTY | J3963 | Solar | 490.0 MW | operational | Brookings, South Dakota |
| West Queue Project BHBE G11 — Coal in Campbell, South Dakota | BHBE G11 | Coal | 475.0 MW | active | Campbell, South Dakota |
| Chappelle Creek - Leland Olds 345kV | GEN-2017-114 | Wind | 450.0 MW | withdrawn | Dewey, South Dakota |
| Big Stone | 6098_1 | Other | 450.0 MW | operational | Grant, South Dakota |
| Big Stone South 345 kV substation | J4135 | Wind | 450.0 MW | withdrawn | Grant, South Dakota |
Top developers in South Dakota
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Basin Electric | 5 | 955 MW |
| BEPC | 4 | 516 MW |
| PrairieWinds SD1 Inc. | 3 | 184 MW |
| Citizens Enterprises Corporation | 3 | 303 MW |
| Black Hills Cheyenne Light Fuel and Power Transmission | 2 | 240 MW |
| Day County Wind, LLC | 2 | 199 MW |
| NorthWestern Energy | 2 | 62 MW |
| Summit Wind Farm | 1 | 90 MW |
| B&B Panhandle Wind,LLC | 1 | 80 MW |
| Energy Efficiency Solar, Inc. dba ACRO Energy Inc. | 1 | 80 MW |
| Northern Wind | 1 | 50 MW |
| Vedauwoo Holdings Black Hills 1 LLC | 1 | 80 MW |
| Crocker Wind | 1 | 200 MW |
| Black Hills Electric Generation LLC | 1 | 100 MW |
| White Wind Farm LLC | 1 | 200 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-22 | Campbell County 230 kV line | proposed_online_date | 2026-12-31 | 2028-12-31 |
| 2026-08-22 | Campbell County 230 kV line | capacity_mw | 98.9 | 98.6 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue; PJM — new-services interconnection queue; Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Get notified when a new project appears in South Dakota.
Start tracking with interXdata