Aurelius 3 Solar (29INR0011)

Aurelius 3 Solar is a 445.4 MW solar interconnection project in Deaf Smith, Texas with a current status of operational. It is proposed to connect at 23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD)..

445.4 MWCapacity
OperationalStatus
Deaf SmithMarket
SolarTechnology

Project facts

Canonical nameAurelius 3 Solar
Queue ID29INR0011
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketDeaf Smith
TechnologySolar
Capacity445.4 MW
StateTexas
CountyDeaf Smith
Point of interconnection23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD).
Requested (queue) date2023-12-04
Proposed in-service date
Operational date2029-03-31
Withdrawn date
DeveloperIP Roman III, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.