Aurelius 3 Solar (29INR0011)
Aurelius 3 Solar is a 445.4 MW solar interconnection project in Deaf Smith, Texas with a current status of operational. It is proposed to connect at 23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD)..
Project facts
| Canonical name | Aurelius 3 Solar |
|---|---|
| Queue ID | 29INR0011 |
| Status | operational |
| Source status | SS Completed, FIS Started, No IA |
| Market | Deaf Smith |
| Technology | Solar |
| Capacity | 445.4 MW |
| State | Texas |
| County | Deaf Smith |
| Point of interconnection | 23908 Deaf Smith station 345 kV. This INR has a 600 MW PUN load at the medium voltage side of the MPTs for a total of 1800 MW PUN load (refer to the substation SLD). |
| Requested (queue) date | 2023-12-04 |
| Proposed in-service date | — |
| Operational date | 2029-03-31 |
| Withdrawn date | — |
| Developer | IP Roman III, LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata