Austin Bayou Storage I (25INR0235)

Austin Bayou Storage I is a 150.7 MW other interconnection project in Brazoria, Texas with a current status of operational. It is proposed to connect at Tap 345 kV Savana 43180 to Seabreeze 43020 - Ckt 27.

150.7 MWCapacity
OperationalStatus
BrazoriaMarket
OtherTechnology

Project facts

Canonical nameAustin Bayou Storage I
Queue ID25INR0235
Statusoperational
Source statusSS Completed, FIS Started, IA
MarketBrazoria
TechnologyOther
Capacity150.7 MW
StateTexas
CountyBrazoria
Point of interconnectionTap 345 kV Savana 43180 to Seabreeze 43020 - Ckt 27
Requested (queue) date2023-03-08
Proposed in-service date
Operational date2027-06-01
Withdrawn date
DeveloperAustin Bayou Solar, LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.