Austin Bayou Storage III (25INR0237)
Austin Bayou Storage III is a 156.6 MW other interconnection project in Brazoria, Texas with a current status of operational. It is proposed to connect at Tap 345 kV Savana 43180 to Seabreeze 43020 - Ckt 27.
156.6 MWCapacity
OperationalStatus
BrazoriaMarket
OtherTechnology
Project facts
| Canonical name | Austin Bayou Storage III |
|---|---|
| Queue ID | 25INR0237 |
| Status | operational |
| Source status | SS Completed, FIS Started, IA |
| Market | Brazoria |
| Technology | Other |
| Capacity | 156.6 MW |
| State | Texas |
| County | Brazoria |
| Point of interconnection | Tap 345 kV Savana 43180 to Seabreeze 43020 - Ckt 27 |
| Requested (queue) date | 2023-03-08 |
| Proposed in-service date | — |
| Operational date | 2027-06-01 |
| Withdrawn date | — |
| Developer | Austin Bayou Solar, LLC |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata