Axtell BESS (28INR0157)

Axtell BESS is a 306.9 MW other interconnection project in McLennan, Texas with a current status of operational. It is proposed to connect at 345 kV Tiger Creek Switch (#3379).

306.9 MWCapacity
OperationalStatus
McLennanMarket
OtherTechnology

Project facts

Canonical nameAxtell BESS
Queue ID28INR0157
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketMcLennan
TechnologyOther
Capacity306.9 MW
StateTexas
CountyMcLennan
Point of interconnection345 kV Tiger Creek Switch (#3379)
Requested (queue) date2024-10-01
Proposed in-service date—
Operational date2029-04-16
Withdrawn date—
DeveloperPP Axtell BESS LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-31poi_name#13401 Tiger Creek Switch 345kV345 kV Tiger Creek Switch (#3379)low
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-12

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.