AZ Queue Project 2023-G5 — Solar+Battery in Mohave County, Arizona

AZ Queue Project 2023-G5 — Solar+Battery in Mohave County, Arizona is a 225.0 MW solar+battery interconnection project in Mohave County, Arizona with a current status of active. It is proposed to connect at White Hills 345- kV Substation.

225.0 MWCapacity
ActiveStatus
AZMarket
Solar+BatteryTechnology

Project facts

Canonical nameAZ Queue Project 2023-G5 — Solar+Battery in Mohave County, Arizona
Queue ID2023-G5
Statusactive
Source status
MarketAZ
TechnologySolar+Battery
Capacity225.0 MW
StateArizona
CountyMohave County
Point of interconnectionWhite Hills 345- kV Substation
Requested (queue) date2023-04-24
Proposed in-service date2026-12-30
Operational date
Withdrawn date
Developer
Utility / transmission ownerWestern Area Power Administration - Desert Southwest Region

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: wapa-dsw-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata