Badger Solar (28INR0212)

Badger Solar is a 280.5 MW solar interconnection project in Upton, Texas with a current status of operational. It is proposed to connect at Tap 345kV 59903 Bearkat - 76000 L_NORTMC5_1Y.

280.5 MWCapacity
OperationalStatus
UptonMarket
SolarTechnology

Project facts

Canonical nameBadger Solar
Queue ID28INR0212
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketUpton
TechnologySolar
Capacity280.5 MW
StateTexas
CountyUpton
Point of interconnectionTap 345kV 59903 Bearkat - 76000 L_NORTMC5_1Y
Requested (queue) date2025-02-12
Proposed in-service date—
Operational date2029-05-25
Withdrawn date—
Developer174 Power Global Properties
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-10-30capacity_mw301.83280.46high
2026-09-30poi_name345 kV North McCamey Substation (Bus# 76000)Tap 345kV 59903 Bearkat - 76000 L_NORTMC5_1Ylow
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-10-30
Data last materially changed2026-10-30
Page data generated2026-11-26

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata