Battery Storage Addition (1394)

Battery Storage Addition is a 284.1 MW battery interconnection project in Middlesex, Connecticut with a current status of withdrawn. It is proposed to connect at POI between 10F-2T-2 and 10F-1T-1 breakers on the 345 kV bus; Northeast Utilities 11631 Substation - Middletown..

284.1 MWCapacity
WithdrawnStatus
CTMarket
BatteryTechnology

Project facts

Canonical nameBattery Storage Addition
Queue ID1394
Statuswithdrawn
Source statusW
MarketCT
TechnologyBattery
Capacity284.1 MW
StateConnecticut
CountyMiddlesex
Point of interconnectionPOI between 10F-2T-2 and 10F-1T-1 breakers on the 345 kV bus; Northeast Utilities 11631 Substation - Middletown.
Requested (queue) date2023-05-04
Proposed in-service date2026-07-01
Operational date
Withdrawn date2025-10-10
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata