Battery Storage is a 160.0 MW battery interconnection project in New Haven, Connecticut with a current status of withdrawn. It is proposed to connect at CT_UI June Street 115KV substation/ Bus ID: 123416.

160.0 MWCapacity
WithdrawnStatus
CTMarket
BatteryTechnology

Project facts

Canonical nameBattery Storage
Queue ID1208
Statuswithdrawn
Source statusW
MarketCT
TechnologyBattery
Capacity160.0 MW
StateConnecticut
CountyNew Haven
Point of interconnectionCT_UI June Street 115KV substation/ Bus ID: 123416
Requested (queue) date2021-12-30
Proposed in-service date2024-12-31
Operational date
Withdrawn date2022-03-08
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.