Battery Storage (1263)
Battery Storage is a 18.9 MW battery interconnection project in Hampshire, Massachusetts with a current status of withdrawn. It is proposed to connect at POI Coordinates: 42.42649, -72.53956, Feeder: 18G6, Express feeder, Owner of POI: WMECO (Eversource), Distribution Voltage Level: 13.8 kV, Substation Voltage Level: 115 kV - 13.8 kV.
Project facts
| Canonical name | Battery Storage |
|---|---|
| Queue ID | 1263 |
| Status | withdrawn |
| Source status | W |
| Market | WMA |
| Technology | Battery |
| Capacity | 18.9 MW |
| State | Massachusetts |
| County | Hampshire |
| Point of interconnection | POI Coordinates: 42.42649, -72.53956, Feeder: 18G6, Express feeder, Owner of POI: WMECO (Eversource), Distribution Voltage Level: 13.8 kV, Substation Voltage Level: 115 kV - 13.8 kV |
| Requested (queue) date | 2022-07-01 |
| Proposed in-service date | 2023-10-27 |
| Operational date | — |
| Withdrawn date | 2023-07-13 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata