Battery Storage (1384)

Battery Storage is a 300.0 MW battery interconnection project in Worcester, Massachusetts with a current status of withdrawn. It is proposed to connect at National Grid's Pratts Junction - Sandy Pond L138W-2 line (115 kV). 2.92 miles from Pratts Junction and 11.95 miles from Sandy Pond (on 115 kV line). Coordinates: 42.493249051839484, -71.7028083287439.

300.0 MWCapacity
WithdrawnStatus
CMAMarket
BatteryTechnology

Project facts

Canonical nameBattery Storage
Queue ID1384
Statuswithdrawn
Source statusW
MarketCMA
TechnologyBattery
Capacity300.0 MW
StateMassachusetts
CountyWorcester
Point of interconnectionNational Grid's Pratts Junction - Sandy Pond L138W-2 line (115 kV). 2.92 miles from Pratts Junction and 11.95 miles from Sandy Pond (on 115 kV line). Coordinates: 42.493249051839484, -71.7028083287439
Requested (queue) date2023-04-26
Proposed in-service date2026-12-31
Operational date
Withdrawn date2024-07-29
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.