Battery Storage (1392)

Battery Storage is a 53.7 MW battery interconnection project in New Haven, Connecticut with a current status of withdrawn. It is proposed to connect at Latitude: 41.492036°, Longitude: -72.762080° -Owner: Connecticut Light and Power Company, Voltage 115 kV, Substation Name: North Wallingford 115 kV Station..

53.7 MWCapacity
WithdrawnStatus
CTMarket
BatteryTechnology

Project facts

Canonical nameBattery Storage
Queue ID1392
Statuswithdrawn
Source statusW
MarketCT
TechnologyBattery
Capacity53.7 MW
StateConnecticut
CountyNew Haven
Point of interconnectionLatitude: 41.492036°, Longitude: -72.762080° -Owner: Connecticut Light and Power Company, Voltage 115 kV, Substation Name: North Wallingford 115 kV Station.
Requested (queue) date2023-05-03
Proposed in-service date2026-09-15
Operational date
Withdrawn date2025-09-23
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata