Battery Storage (1399)
Battery Storage is a 92.4 MW battery interconnection project in Hampden, Massachusetts with a current status of withdrawn. It is proposed to connect at The proposed POI is Buck Pond 115 kV substation, share gen leadline with QP1117..
92.4 MWCapacity
WithdrawnStatus
WMAMarket
BatteryTechnology
Project facts
| Canonical name | Battery Storage |
|---|---|
| Queue ID | 1399 |
| Status | withdrawn |
| Source status | W |
| Market | WMA |
| Technology | Battery |
| Capacity | 92.4 MW |
| State | Massachusetts |
| County | Hampden |
| Point of interconnection | The proposed POI is Buck Pond 115 kV substation, share gen leadline with QP1117. |
| Requested (queue) date | 2023-05-18 |
| Proposed in-service date | 2027-05-31 |
| Operational date | — |
| Withdrawn date | 2025-10-11 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Follow this project and get an alert when its status, capacity, developer, or schedule changes.
Start tracking with interXdata