Battery Storage (1509)
Battery Storage is a 152.8 MW battery interconnection project in Worcester, Massachusetts with a current status of withdrawn. It is proposed to connect at 3-breaker ring bus tapping the W175 line. ESA sub located approximately 0.23 miles from West Charlton 115 kV substation at current coordinates 42° 8'10.02"N 72° 1'30.37"W.
Project facts
| Canonical name | Battery Storage |
|---|---|
| Queue ID | 1509 |
| Status | withdrawn |
| Source status | W |
| Market | CMA |
| Technology | Battery |
| Capacity | 152.8 MW |
| State | Massachusetts |
| County | Worcester |
| Point of interconnection | 3-breaker ring bus tapping the W175 line. ESA sub located approximately 0.23 miles from West Charlton 115 kV substation at current coordinates 42° 8'10.02"N 72° 1'30.37"W |
| Requested (queue) date | 2024-04-03 |
| Proposed in-service date | 2027-12-31 |
| Operational date | — |
| Withdrawn date | 2025-10-07 |
| Developer | — |
| Utility / transmission owner | ISO-NE |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-08-04 | new_project | — | withdrawn | high |
Explore related data
Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.