Battery Storage (1541)

Battery Storage is a 101.0 MW battery interconnection project in Middlesex, Massachusetts with a current status of withdrawn. It is proposed to connect at 42.385528, -71.490823 on Hudson-Sudbury 115kV line.

101.0 MWCapacity
WithdrawnStatus
BOSTMarket
BatteryTechnology

Project facts

Canonical nameBattery Storage
Queue ID1541
Statuswithdrawn
Source statusW
MarketBOST
TechnologyBattery
Capacity101.0 MW
StateMassachusetts
CountyMiddlesex
Point of interconnection42.385528, -71.490823 on Hudson-Sudbury 115kV line
Requested (queue) date2024-05-28
Proposed in-service date2028-05-31
Operational date
Withdrawn date2025-10-11
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.