Bay Shore - Lallendorf 345 kV (AH1-690 - moved to TC2)

Bay Shore - Lallendorf 345 kV is a 1,475.0 MW gas interconnection project in Lucas, Ohio with a current status of withdrawn.

1,475.0 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameBay Shore - Lallendorf 345 kV
Queue IDAH1-690 - moved to TC2
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity1,475.0 MW
StateOhio
CountyLucas
Point of interconnection
Requested (queue) date2025-04-03
Proposed in-service date2031-03-01
Operational date
Withdrawn date2025-11-18
Developer
Utility / transmission ownerATSI

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata