Ohio Interconnection Projects
interXdata tracks 1,629 interconnection projects in Ohio representing 163,348 MW of requested capacity. The dominant technology by capacity is Gas. The most active counties are Butler, Montgomery, Madison.
1,629Total projects
133Active
628Operational
842Withdrawn
163,348 MWRequested capacity
16,481 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Gas | 332 | 53,995 MW |
| Solar | 722 | 52,832 MW |
| Other | 259 | 22,179 MW |
| Wind | 146 | 18,509 MW |
| Battery | 148 | 12,516 MW |
| Coal | 8 | 2,291 MW |
| Solar+Battery | 10 | 942 MW |
| Nuclear | 3 | 74 MW |
| Solar+Wind | 1 | 10 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Butler | 50 | 4,044 MW |
| Montgomery | 49 | 1,726 MW |
| Madison | 45 | 4,872 MW |
| Hardin | 43 | 3,813 MW |
| Highland | 43 | 4,388 MW |
| Pickaway | 41 | 5,800 MW |
| Paulding | 41 | 2,566 MW |
| Union | 38 | 4,921 MW |
| Lucas | 35 | 7,971 MW |
| Van Wert | 35 | 5,101 MW |
| Hancock | 35 | 2,700 MW |
| Ross | 33 | 2,106 MW |
| Wood | 33 | 3,635 MW |
| Trumbull | 32 | 7,736 MW |
| Champaign | 31 | 2,478 MW |
| Defiance | 31 | 2,144 MW |
| Franklin | 31 | 1,717 MW |
| Lorain | 30 | 1,587 MW |
| Marion | 30 | 1,486 MW |
| Williams | 30 | 695 MW |
| Cuyahoga | 28 | 297 MW |
| Logan | 26 | 2,541 MW |
| Clermont | 26 | 2,178 MW |
| Crawford | 25 | 2,761 MW |
| Licking | 24 | 1,660 MW |
| Henry | 23 | 1,491 MW |
| Hamilton | 22 | 2,692 MW |
| Washington | 22 | 3,987 MW |
| Ashtabula | 22 | 1,451 MW |
| Morrow | 21 | 1,724 MW |
| Darke | 21 | 1,278 MW |
| Adams | 20 | 2,262 MW |
| Jefferson | 20 | 6,060 MW |
| Brown | 19 | 935 MW |
| Summit | 19 | 847 MW |
| Wayne | 18 | 539 MW |
| Fulton | 18 | 2,325 MW |
| Huron | 18 | 2,723 MW |
| Muskingum | 17 | 2,851 MW |
| Richland | 17 | 727 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Sammis 345kV | R68 | Other | 1,940.0 MW | withdrawn | Jefferson, Ohio |
| W. H. Sammis 345kV | I07 | Other | 1,860.0 MW | withdrawn | Jefferson, Ohio |
| Bay Shore - Lallendorf 345 kV | AH1-690 - moved to TC2 | Gas | 1,475.0 MW | withdrawn | Lucas, Ohio |
| PJM Queue Project AH1-690 — Gas in Lucas, Ohio | AH1-690 | Gas | 1,475.0 MW | withdrawn | Lucas, Ohio |
| Perry | 6020_1 | Other | 1,311.6 MW | operational | Lake, Ohio |
| Killen 345kV | S12 | Other | 1,300.0 MW | withdrawn | Adams, Ohio |
| Gavin Power, LLC | 8102_1 | Other | 1,300.0 MW | operational | Gallia, Ohio |
| Sammis - South Canton 345 kV | AH1-680 - moved to TC2 | Gas | 1,300.0 MW | active | Carroll, Ohio |
| Gavin Power, LLC | 8102_2 | Other | 1,300.0 MW | operational | Gallia, Ohio |
| PJM Queue Project AH1-680 — Gas in Carroll, Ohio | AH1-680 | Gas | 1,300.0 MW | active | Carroll, Ohio |
| Marysville-Flatlick 765kV | AC1-096 | Gas | 1,277.0 MW | withdrawn | Pickaway, Ohio |
| Muskingum River 345 kV Phase I | AD1-090 | Gas | 1,260.0 MW | withdrawn | Washington, Ohio |
| Marysville-Flatlick 765kV | AB2-080 | Gas | 1,200.0 MW | withdrawn | Pickaway, Ohio |
| MISO Queue Project G482 — Coal in Ashtabula, Ohio | G482 | Coal | 1,200.0 MW | withdrawn | Ashtabula, Ohio |
| Mountaineer-Belmont 765kV | N42 | Other | 1,200.0 MW | withdrawn | Meigs, Ohio |
| Highland-Lordstown 345 kV | AE2-013 | Gas | 1,170.0 MW | withdrawn | Trumbull, Ohio |
| Highland-Lordstown 1 & 2 345 kV | AE1-213 | Gas | 1,170.0 MW | withdrawn | Trumbull, Ohio |
| Highland-Sammis 345kV | AA1-123 | Gas | 1,152.0 MW | operational | Columbiana, Ohio |
| Kammer-Vassell 765kV | AB2-067 | Gas | 1,100.0 MW | operational | Guernsey, Ohio |
| Sammis–Star 345kV | Y2-085 | Gas | 1,050.0 MW | withdrawn | Carroll, Ohio |
| Nottingham 138kV | AC1-103 | Gas | 1,050.0 MW | withdrawn | Harrison, Ohio |
| Sporn - Waterford 345kV | P54 | Other | 1,035.0 MW | withdrawn | Meigs, Ohio |
| Bayshore-GM Powertrain 138 kV & Lallendorf 345kV | AB1-107 | Gas | 955.0 MW | withdrawn | Lucas, Ohio |
| Highland-Hanna 345kV | AD2-057 | Gas | 940.0 MW | withdrawn | Trumbull, Ohio |
| Highland-Hanna 345kV | AB1-105 | Gas | 940.0 MW | operational | Trumbull, Ohio |
| Davis Besse | 6149_1 | Other | 925.2 MW | operational | Ottawa, Ohio |
| Highland-Sammis 345kV & Highland-Mansfield 345kV | Z2-028 | Gas | 800.0 MW | operational | Trumbull, Ohio |
| Zimmer 345 kV | AJ1-008 | Solar | 800.0 MW | withdrawn | Clermont, Ohio |
| MISO Queue Project G083 — Other in Hamilton, Ohio | G083 | Other | 800.0 MW | withdrawn | Hamilton, Ohio |
| Bay Shore-Fostoria Central 345kV & Bayshore-Monroe 345kV | Y1-069 | Gas | 799.0 MW | operational | Lucas, Ohio |
Top developers in Ohio
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Riverlake Energy, LLC | 7 | 631 MW |
| Invenergy | 6 | 337 MW |
| Cardinal Energy Storage East, LLC | 4 | 1,900 MW |
| TerraForm Twin Creeks Solar, LLC | 3 | 128 MW |
| Swamp Fox Solar, LLC | 2 | 50 MW |
| Reserve Energy Exploration Company | 2 | 100 MW |
| Crossroads Solar I, LLC | 2 | 30 MW |
| Hamden Energy LLC | 2 | 160 MW |
| Orchid Acres Solar Project, LLC | 2 | 400 MW |
| Chinchilla Solar LLC | 2 | 105 MW |
| Butterfly Meadows Solar Project, LLC | 2 | 400 MW |
| Dragonfly Fields Solar Project, LLC | 2 | 98 MW |
| Mink Solar LLC | 2 | 324 MW |
| Williams County Solar, LLC | 2 | 296 MW |
| Wombat Solar LLC | 2 | 514 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-11-19 | Congress-Toronto 138 kV | status | suspended | withdrawn |
| 2026-11-13 | West Newton-Lynn 138 kV | status | suspended | active |
| 2026-11-13 | West Newton-Lynn 138 kV | proposed_online_date | 2026-01-14 | 2029-01-14 |
| 2026-11-03 | Elk 138kV | status | active | suspended |
| 2026-11-01 | Stark Solar, LLC | proposed_online_date | 2027-03-01 | 2027-08-01 |
| 2026-11-01 | Nottingham Solar | proposed_online_date | 2026-12-01 | 2027-03-01 |
| 2026-11-01 | Steubenville Solar | proposed_online_date | 2027-03-01 | 2028-06-01 |
| 2026-11-01 | Mark Center Solar Project | operational_date | — | 2026-09-01 |
| 2026-11-01 | Mark Center Solar Project | proposed_online_date | 2026-09-01 | — |
| 2026-11-01 | Mark Center Solar Project | capacity_mw | 90.0 | 94 |
| 2026-11-01 | Mark Center Solar Project | status | active | operational |
| 2026-10-31 | Gunn Road 345 kV | proposed_online_date | 2026-12-31 | — |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.