BBEC - Camp Sub (L0509)

BBEC - Camp Sub is a 11.0 MW other interconnection project in Franklin, Washington with a current status of active. It is proposed to connect at Scooteney Substation.

11.0 MWCapacity
ActiveStatus
WAMarket
OtherTechnology

Project facts

Canonical nameBBEC - Camp Sub
Queue IDL0509
Statusactive
Source statusSTUDY
MarketWA
TechnologyOther
Capacity11.0 MW
StateWashington
CountyFranklin
Point of interconnectionScooteney Substation
Requested (queue) date2021-11-22
Proposed in-service date2025-03-28
Operational date
Withdrawn date
DeveloperBig Bend Electric Cooperative, Inc.
Utility / transmission ownerBonneville Power Administration

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectactivehigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: bpa-oasis. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata