Beaver-Davis Besse 345 kV II (AD1-103)

Beaver-Davis Besse 345 kV II is a 500.4 MW wind interconnection project in Huron, Ohio with a current status of withdrawn.

500.4 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameBeaver-Davis Besse 345 kV II
Queue IDAD1-103
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity500.4 MW
StateOhio
CountyHuron
Point of interconnection
Requested (queue) date2017-09-22
Proposed in-service date2020-12-18
Operational date
Withdrawn date2022-07-13
Developer
Utility / transmission ownerATSI

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.