Beecher Energy - Distribution Cener #36 (Q66)

Beecher Energy - Distribution Cener #36 is a 2.1 MW gas interconnection project in Will, Illinois with a current status of withdrawn.

2.1 MWCapacity
WithdrawnStatus
Market
GasTechnology

Project facts

Canonical nameBeecher Energy - Distribution Cener #36
Queue IDQ66
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyGas
Capacity2.1 MW
StateIllinois
CountyWill
Point of interconnection
Requested (queue) date2006-07-14
Proposed in-service date2007-06-01
Operational date
Withdrawn date2013-10-10
Developer
Utility / transmission ownerComEd

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.