Benton Solar II (E0020)

Benton Solar II is a 105.8 MW solar interconnection project in Benton, Minnesota with a current status of active. It is proposed to connect at Benton County 115kV Substation.

105.8 MWCapacity
ActiveStatus
MISOMarket
SolarTechnology

Project facts

Canonical nameBenton Solar II
Queue IDE0020
Statusactive
Source statusactive
MarketMISO
TechnologySolar
Capacity105.8 MW
StateMinnesota
CountyBenton
Point of interconnectionBenton County 115kV Substation
Requested (queue) date2025-08-06
Proposed in-service date2028-02-25
Operational date
Withdrawn date
DeveloperXcel Energy
Utility / transmission ownerXcel/SPS

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.