Berry Hill 138 kV is a 125.0 MW solar interconnection project in Pittsylvania, Virginia with a current status of active.

125.0 MWCapacity
ActiveStatus
—Market
SolarTechnology

Project facts

Canonical nameBerry Hill 138 kV
Queue IDAF1-049
Statusactive
Source statusUnder Construction
Market—
TechnologySolar
Capacity125.0 MW
StateVirginia
CountyPittsylvania
Point of interconnection—
Requested (queue) date2019-07-12
Proposed in-service date2027-03-30
Operational date—
Withdrawn date—
Developer—
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_project—activehigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.