Virginia Interconnection Projects
interXdata tracks 2,594 interconnection projects in Virginia representing 198,372 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are Chesterfield, Brunswick, Halifax.
2,594Total projects
294Active
964Operational
1,315Withdrawn
198,372 MWRequested capacity
35,742 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 1,218 | 77,580 MW |
| Gas | 510 | 52,940 MW |
| Battery | 447 | 35,457 MW |
| Wind | 49 | 13,491 MW |
| Other | 335 | 12,328 MW |
| Offshore Wind | 5 | 4,089 MW |
| Solar+Battery | 30 | 2,486 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| Chesterfield | 103 | 7,019 MW |
| Brunswick | 90 | 10,429 MW |
| Halifax | 82 | 5,919 MW |
| Mecklenburg | 77 | 4,210 MW |
| Prince William | 77 | 5,980 MW |
| Greensville | 75 | 9,966 MW |
| Pittsylvania | 69 | 4,605 MW |
| Charles City | 67 | 5,456 MW |
| Accomack | 66 | 2,445 MW |
| Caroline | 66 | 5,130 MW |
| Amelia | 62 | 347 MW |
| Fauquier | 58 | 4,728 MW |
| Surry | 56 | 5,536 MW |
| City Of Chesapeake | 56 | 9,043 MW |
| King And Queen | 55 | 575 MW |
| Louisa | 54 | 6,691 MW |
| Pulaski | 51 | 1,916 MW |
| Sussex | 47 | 5,751 MW |
| Rockingham | 46 | 1,650 MW |
| Hanover | 45 | 4,728 MW |
| Fluvanna | 40 | 5,854 MW |
| Campbell | 40 | 1,568 MW |
| Southampton | 40 | 1,789 MW |
| Charlotte | 39 | 3,090 MW |
| Henrico | 39 | 701 MW |
| Buckingham | 37 | 3,255 MW |
| Isle Of Wight | 35 | 2,862 MW |
| Frederick | 30 | 1,863 MW |
| Prince George | 30 | 2,037 MW |
| City Of Suffolk | 29 | 1,616 MW |
| Henry | 28 | 2,243 MW |
| Orange | 28 | 3,708 MW |
| Culpeper | 28 | 1,350 MW |
| Loudoun | 28 | 4,242 MW |
| Augusta | 25 | 1,982 MW |
| Westmoreland | 24 | 641 MW |
| Unknown | 24 | 1,783 MW |
| Bedford | 24 | 607 MW |
| King George | 21 | 1,583 MW |
| Lunenburg | 21 | 1,545 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Coastal Virginia Offshore Wind (CVOW) Commercial Project | 64550_CVOWC | Wind | 2,640.0 MW | active | Virginia |
| Heritage-Carson | Z1-086 | Gas | 1,681.0 MW | operational | Greensville, Virginia |
| Chickahominy 500kV | AC1-107 | Gas | 1,600.0 MW | withdrawn | Charles City, Virginia |
| North Anna 500kV | Q65 | Other | 1,594.0 MW | withdrawn | Louisa, Virginia |
| Chesterfield 230kV | X2-082 | Gas | 1,575.0 MW | withdrawn | Chesterfield, Virginia |
| Brunswick 500kV | Y2-097 | Gas | 1,551.0 MW | withdrawn | Brunswick, Virginia |
| Carson-Wake 500kV | X2-076 | Gas | 1,525.5 MW | operational | Brunswick, Virginia |
| PJM Queue Project AH1-676 — Gas in Orange, Virginia | AH1-676 | Gas | 1,294.6 MW | withdrawn | Orange, Virginia |
| Gordonsville 230 kV | AH1-676 - moved to TC2 | Gas | 1,294.6 MW | withdrawn | Orange, Virginia |
| Chickahominy 500kV | AB2-068 | Gas | 1,060.0 MW | withdrawn | Charles City, Virginia |
| Four Rivers 500kV | T168 | Gas | 1,010.0 MW | withdrawn | Hanover, Virginia |
| North Anna | 6168_2 | Other | 979.7 MW | operational | Louisa, Virginia |
| North Anna | 6168_1 | Other | 979.7 MW | operational | Louisa, Virginia |
| Chesapeake 230 kV | AE2-007 | Gas | 967.6 MW | withdrawn | City Of Chesapeake, Virginia |
| Burches Hill 500kV | E22 | Gas | 960.0 MW | withdrawn | Prince William, Virginia |
| Possum Point 230kV | V1-031 | Gas | 950.0 MW | withdrawn | Prince William, Virginia |
| Front Royal 500kV | V2-030 | Gas | 950.0 MW | operational | Warren, Virginia |
| Surry | 3806_1 | Other | 847.5 MW | operational | Surry, Virginia |
| Surry | 3806_2 | Other | 847.5 MW | operational | Surry, Virginia |
| Chesapeake 230kV | AB2-051 | Gas | 840.0 MW | withdrawn | City Of Chesapeake, Virginia |
| CVOW 2, OSS 2 – T2G07 | AF1-124 | Offshore Wind | 836.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-124 - moved to TC1 | Wind | 836.0 MW | operational | City Of Chesapeake, Virginia |
| CVOW 1, OSS 1 - T1L11 | AF1-123 | Offshore Wind | 833.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-123 - moved to TC1 | Wind | 833.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-125 - moved to TC1 | Wind | 820.0 MW | operational | City Of Chesapeake, Virginia |
| CVOW 3, OSS 3 – T3G15 | AF1-125 | Offshore Wind | 820.0 MW | active | City Of Chesapeake, Virginia |
| Virginia Beach 230 kV | AE1-067 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Virginia Beach 230 kV | AE1-066 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Landstown 230 kV | AE2-124 - moved to TC1 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| PJM Queue Project AE2-123 — Offshore Wind in City Of Virginia Beach, Virginia | AE2-123 | Offshore Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
Top developers in Virginia
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| Virginia Electric and Power Company | 40 | 7,743 MW |
| ACE Development Company, LLC | 9 | 873 MW |
| RWE Solar Development, LLC | 8 | 742 MW |
| Invenergy | 5 | 452 MW |
| NW-Rocky Ford LLC | 5 | 75 MW |
| CV-Tollhouse LLC | 4 | 80 MW |
| Cardinal Energy Storage East, LLC | 4 | 1,975 MW |
| Bellflower Holdings, LLC | 4 | 600 MW |
| Amelia Energy Facility, LLC | 4 | 106 MW |
| Summersweet Energy Center, LLC | 4 | 150 MW |
| Vista Energy Facility, LLC | 3 | 95 MW |
| Delorean Power LLC dba Lightshift Energy | 3 | 280 MW |
| Ameresco, Inc. | 3 | 41 MW |
| Urban Grid Solar | 3 | 460 MW |
| Aries Solar Project LLC | 2 | 150 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-11-21 | Hazel Hollow-Glen Lyn #1 138 kV | proposed_online_date | 2028-02-28 | 2029-02-28 |
| 2026-11-21 | Lexington-Low Moor 230kV | operational_date | 2026-12-31 | 2026-11-25 |
| 2026-11-03 | East Danville - Roxborough 230 kV | proposed_online_date | 2027-10-01 | 2028-10-01 |
| 2026-11-03 | East Danville - Roxborough 230 kV | proposed_online_date | 2027-10-01 | 2028-10-01 |
| 2026-11-03 | Hopewell-Surry 230 kV | withdrawn_date | — | 2026-07-23 |
| 2026-11-01 | Jarratt Energy Facility | new_project | — | active |
| 2026-11-01 | Jarratt Energy Facility | new_project | — | active |
| 2026-11-01 | Jarratt Energy Facility | new_project | — | active |
| 2026-11-01 | Blue Ridge Solar | proposed_online_date | 2027-03-01 | 2027-05-01 |
| 2026-11-01 | Railroad Energy Center, LLC | proposed_online_date | 2026-10-01 | 2026-12-01 |
| 2026-11-01 | Bethlehem Energy Center, LLC - (VA) | proposed_online_date | 2026-10-01 | 2026-12-01 |
| 2026-11-01 | Cerulean Solar | proposed_online_date | 2026-09-01 | 2026-12-01 |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; lgeku-oasis; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.