Bethpage Large Battery Energy Storage Project (1202)

Bethpage Large Battery Energy Storage Project is a 24.0 MW battery interconnection project in Nassau, New York with a current status of withdrawn. It is proposed to connect at Grumman 69kV substation.

24.0 MWCapacity
WithdrawnStatus
KMarket
BatteryTechnology

Project facts

Canonical nameBethpage Large Battery Energy Storage Project
Queue ID1202
Statuswithdrawn
Source status0
MarketK
TechnologyBattery
Capacity24.0 MW
StateNew York
CountyNassau
Point of interconnectionGrumman 69kV substation
Requested (queue) date2021-06-11
Proposed in-service date2024-09-30
Operational date
Withdrawn date
DeveloperCalpine Energy Services, L.P.
Utility / transmission ownerLIPA

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.