LIPA — Interconnection Queue Projects
LIPA is associated with 275 tracked interconnection projects representing 65,392 MW of requested capacity.
Entity resolution: this utility / transmission entity rolls up 3 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Wind | 39 | 32,207 MW |
| Other | 54 | 14,874 MW |
| Battery | 147 | 14,801 MW |
| Gas | 16 | 2,948 MW |
| Solar | 19 | 563 MW |
Portfolio by market
| Market | Projects |
|---|---|
| NYISO | 29 |
Geographic footprint
| State | Projects |
|---|---|
| New York | 274 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Atlantic Shores Offshore Wind Bight 3 | 1339 | Wind | 2,100.0 MW | withdrawn | Suffolk, New York |
| EI Empire ESS II | 1186 | Other | 1,440.0 MW | withdrawn | Nassau, New York |
| Vineyard Wind II | 1011 | Wind | 1,403.0 MW | withdrawn | Suffolk, New York |
| NY Wind - Pilgrim CSR | 1503 | Other | 1,400.0 MW | withdrawn | Suffolk County, New York |
| NY Wind - Pilgrim Uprate | 1460 | Wind | 1,400.0 MW | withdrawn | Suffolk County, New York |
| NY Wind - New Bridge Road | 1057 | Wind | 1,325.0 MW | withdrawn | Nassau, New York |
| Community OSW Barrett 3 | 1653 | Wind | 1,310.0 MW | withdrawn | Nassau, New York |
| Attentive Energy 1 | 1385 | Wind | 1,310.0 MW | withdrawn | Suffolk, New York |
| EI Glenwood Landing | 1022 | Wind | 1,300.0 MW | withdrawn | Nassau, New York |
| EI East Shoreham | 1021 | Wind | 1,300.0 MW | withdrawn | Suffolk, New York |
| EI Fort Salonga | 1020 | Wind | 1,300.0 MW | withdrawn | Suffolk, New York |
| NY Wind - Pilgrim | 1058 | Wind | 1,276.0 MW | withdrawn | Suffolk, New York |
| NY Wind - Shore Road | 1056 | Wind | 1,272.0 MW | withdrawn | Nassau, New York |
| EI Oceanside 2 | 0959 | Wind | 1,260.0 MW | withdrawn | Nassau, New York |
| OW Ocean Winds East 2 | 1176 | Wind | 1,200.0 MW | withdrawn | Nassau, New York |
| Juno Power Express | 0680 | Other | 1,200.0 MW | withdrawn | Suffolk, New York |
| OW Ocean Winds East 1 | 1175 | Wind | 1,200.0 MW | withdrawn | Nassau, New York |
| Community OSW Barrett 1 | 1373 | Wind | 1,100.0 MW | withdrawn | Nassau, New York |
| Community OSW Valley Stream 1 | 1369 | Wind | 1,100.0 MW | withdrawn | Nassau, New York |
| Community OSW Ruland Road 1 | 1370 | Wind | 1,100.0 MW | withdrawn | Suffolk, New York |
| NY Wind Holbrook 2 Uprate | 1045 | Wind | 1,050.0 MW | withdrawn | Suffolk, New York |
| NY Wind Brookhaven | 0765 | Wind | 880.0 MW | withdrawn | Suffolk, New York |
| Sunrise Wind | 0766 | Wind | 880.0 MW | active | Suffolk, New York |
| El Melville | 0738 | Wind | 816.0 MW | withdrawn | Suffolk, New York |
| NY Ocean Grid - Canal | 0754 | Wind | 800.0 MW | withdrawn | Suffolk, New York |
| Juno Power Express 2 | 0792 | Other | 800.0 MW | withdrawn | Suffolk, New York |
| Long Island Offshore AC | 0702 | Wind | 800.0 MW | withdrawn | Suffolk, New York |
| NY Ocean Grid - Shoreham | 0755 | Wind | 800.0 MW | withdrawn | Suffolk, New York |
| Kitchen | 0037 | — | 750.0 MW | withdrawn | New York |
| Offshore Wind | 0327 | Wind | 700.0 MW | withdrawn | NY-Suffolk, New York |
| Project Neptune DC PJM-LI | 0094 | Other | 660.0 MW | operational | Nassau, NY-NJ |
| NU CT-LI HVDC Cable | 0101 | — | 660.0 MW | withdrawn | New York |
| PJM-Barrett HVDC | 0134 | — | 650.0 MW | withdrawn | New York |
| Sandlot | 1485 | Battery | 600.0 MW | withdrawn | Suffolk County, New York |
| CT-LI AC Tie-line | 0015 | — | 600.0 MW | withdrawn | New York |
| Caithness Long Island II | 0401 | Other | 599.0 MW | withdrawn | Suffolk, New York |
| Brookhaven Energy | 0032 | Gas | 580.0 MW | withdrawn | Suffolk, New York |
| SE Long Island | 0108 | Gas | 575.0 MW | withdrawn | Suffolk, New York |
| AES Smithtown Gen | 0050 | — | 510.0 MW | withdrawn | New York |
| Poseidon Offshore | 0363 | Wind | 500.0 MW | withdrawn | Ny - Suffolk, New York |
| Oyster Shore BESS | 1085 | Battery | 500.0 MW | withdrawn | Nassau, New York |
| LI Cable - Phase 1 | 0291 | Wind | 440.0 MW | withdrawn | Suffolk, New York |
| NY Wind Canal | 0764 | Wind | 440.0 MW | withdrawn | Suffolk, New York |
| Port Jefferson Energy Storage | 1546 | Battery | 400.0 MW | withdrawn | Suffolk, New York |
| Holbrook II Energy Storage | 1548 | Battery | 400.0 MW | withdrawn | Suffolk, New York |
| Green Isles Energy Storage | C24-351 | Battery | 400.0 MW | withdrawn | Suffolk, New York |
| PJM-Newbridge Rd HVDC | 0126 | Other | 350.0 MW | withdrawn | New York |
| CT-LI DC Tie-line | 0004 | Other | 330.0 MW | operational | Shoreham, New York |
| Oceanside Energy Center | 0074 | — | 330.0 MW | withdrawn | New York |
| Caithness Long Island | 0107 | Gas | 310.0 MW | operational | Suffolk, New York |
| Brookhaven Energy Ext. | 0049 | — | 300.0 MW | withdrawn | New York |
| CT-Ruland, LI DC Tie | 0053 | — | 300.0 MW | withdrawn | New York |
| East Setauket Energy Storage II | 1505 | Battery | 300.0 MW | withdrawn | Suffolk, New York |
| CT-Pilgrim, LI DC Tie | 0054 | — | 300.0 MW | withdrawn | New York |
| oyster shore III | 1431 | Battery | 300.0 MW | withdrawn | Nassau, New York |
| Ruland Energy | 0044 | — | 300.0 MW | withdrawn | New York |
| Holbrook Energy | 0042 | — | 300.0 MW | withdrawn | New York |
| QMB1 Energy Storage | 1310 | Battery | 300.0 MW | withdrawn | Nassua, New York |
| PPL Kings Park Ext. | 0048 | — | 300.0 MW | withdrawn | New York |
| EGC BESS | 1084 | Battery | 300.0 MW | withdrawn | Nassau, New York |
| Brookhaven Energy | 0046 | — | 300.0 MW | withdrawn | New York |
| Ruland Energy Ext. | 0068 | — | 300.0 MW | withdrawn | New York |
| PPL Kings Park | 0043 | — | 300.0 MW | withdrawn | New York |
| Winergy Long Island Wind | 0273 | Wind | 299.0 MW | withdrawn | Suffolk, New York |
| Wildwood-Riverhead Energy Storage | 0973 | Battery | 293.5 MW | withdrawn | Suffolk, New York |
| LI Cable - Phase 2b | 0293 | Wind | 280.0 MW | withdrawn | Suffolk, New York |
| Glenwood | 0536 | Other | 275.0 MW | withdrawn | Suffolk, New York |
| Empire Interconnection | 0533 | Other | 275.0 MW | withdrawn | Nassau, New York |
| Oyster shore Energy storage | C24-075 | Battery | 275.0 MW | withdrawn | Nassau, New York |
| Island Park Energy Center CCPP | 0427 | Gas | 268.0 MW | withdrawn | Nassau, New York |
| Island Park Energy Center SCPP | 0428 | Gas | 262.0 MW | withdrawn | Nassau, New York |
| Holbrook Energy Storage II | C24-068 | Battery | 260.0 MW | withdrawn | Suffolk, New York |
| Intrepid Storage 138 | 0918 | Battery | 250.0 MW | withdrawn | Nassau, New York |
| Shoreham Gen Station | 0021 | — | 250.0 MW | withdrawn | New York |
| Newbridge-Ruland Storage | 1333 | Battery | 250.0 MW | withdrawn | Nassau, New York |
| Spagnoli Road CC Unit | 0020 | Gas | 250.0 MW | withdrawn | Suffolk, New York |
| East Setauket Storage II | C24-183 | Battery | 248.0 MW | active | Suffolk, New York |
| LI Cable - Phase 2a | 0292 | Wind | 220.0 MW | withdrawn | Suffolk, New York |
| Community OSW Ruland Road 2 | 1376 | Wind | 210.0 MW | withdrawn | Suffolk, New York |
| Community OSW Barrett 2 | 1379 | Wind | 210.0 MW | withdrawn | Nassau, New York |
Recent material changes
No material field-level changes have been recorded against these projects since the baseline snapshot. interXdata records changes as new source snapshots are ingested and diffed.
Explore related data
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.