Big Cajun II 500kV Substation (R5086)

Big Cajun II 500kV Substation is a 593.0 MW battery interconnection project in Pointe Coupee, Louisiana with a current status of operational. It is proposed to connect at Big Cajun II 500kV Substation.

593.0 MWCapacity
OperationalStatus
Market
BatteryTechnology

Project facts

Canonical nameBig Cajun II 500kV Substation
Queue IDR5086
Statusoperational
Source statusActive
Market
TechnologyBattery
Capacity593.0 MW
StateLouisiana
CountyPointe Coupee
Point of interconnectionBig Cajun II 500kV Substation
Requested (queue) date2025-10-17
Proposed in-service date2028-02-29
Operational date2028-02-29
Withdrawn date
Developer
Utility / transmission ownerMISO

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectoperationalhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata