MISO — Interconnection Queue Projects
MISO is associated with 5,585 tracked interconnection projects representing 1,073,892 MW of requested capacity.
Entity resolution: single source organization name; no cluster merge applied.
5,585Projects
110Active
2,105Operational
3,370Withdrawn
1,073,892 MWRequested capacity
1Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 2,250 | 366,027 MW |
| Wind | 1,525 | 258,969 MW |
| Gas | 397 | 181,055 MW |
| Other | 465 | 111,641 MW |
| Battery | 752 | 108,448 MW |
| Coal | 94 | 29,548 MW |
| Nuclear | 27 | 9,285 MW |
| Hydro | 18 | 4,196 MW |
| Solar+Battery | 10 | 2,174 MW |
| Gas+Battery | 1 | 530 MW |
| Other Storage | 6 | 420 MW |
| Solar+Other | 2 | 410 MW |
| Wind+Other | 1 | 400 MW |
| Diesel | 32 | 326 MW |
| Gas+Other Storage | 1 | 270 MW |
| Wind+Battery | 1 | 150 MW |
| Solar+Gas | 1 | 30 MW |
| Geothermal+Other | 1 | 8 MW |
| Wind+Gas | 1 | 5 MW |
Portfolio by market
| Market | Projects |
|---|---|
| MISO | 1,766 |
Geographic footprint
| State | Projects |
|---|---|
| Michigan | 743 |
| Minnesota | 736 |
| Illinois | 619 |
| Indiana | 589 |
| Iowa | 474 |
| Louisiana | 449 |
| Arkansas | 447 |
| Wisconsin | 435 |
| Mississippi | 215 |
| North Dakota | 198 |
| Missouri | 158 |
| South Dakota | 122 |
| Texas | 105 |
| Kentucky | 80 |
| Ohio | 42 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| MISO Queue Project J292 — Hydro in Churchill, MB | J292 | Hydro | 3,576.0 MW | operational | Churchill, MB |
| Schahfer CCGTs | E0042 | Gas | 2,739.8 MW | active | Jasper, Indiana |
| MISO Queue Project J236 — Wind in White, Indiana | J236 | Wind | 2,400.0 MW | withdrawn | White, Indiana |
| MISO Queue Project G166 — Other in Sheboygan, Wisconsin | G166 | Other | 2,400.0 MW | withdrawn | Sheboygan, Wisconsin |
| MISO Queue Project J371 — Nuclear in Ogle, Illinois | J371 | Nuclear | 2,325.0 MW | withdrawn | Ogle, Illinois |
| SIOUX | J4241 | — | 2,220.0 MW | operational | St. Charles, — |
| SIOUX | J3996 | Gas | 2,220.0 MW | operational | St. Charles, Missouri |
| MISO Queue Project J4256 — Generation in an unlisted county, the U.S. | J4256 | — | 2,015.0 MW | operational | — |
| MISO Queue Project G705 — Wind in Hand, South Dakota | G705 | Wind | 2,000.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project PQ0002 — Other in Cerro Gordo, Iowa | PQ0002 | Other | 2,000.0 MW | withdrawn | Cerro Gordo, Iowa |
| MISO Queue Project G903 — Wind in Wright, Minnesota | G903 | Wind | 2,000.0 MW | withdrawn | Wright, Minnesota |
| MISO Queue Project J4176 — Generation in an unlisted county, the U.S. | J4176 | — | 1,750.0 MW | withdrawn | — |
| MISO Queue Project G733 — Nuclear in Callaway, Missouri | G733 | Nuclear | 1,650.0 MW | withdrawn | Callaway, Missouri |
| MISO Queue Project APP-100103 — Gas in an unlisted county, Louisiana | APP-100103 | Gas | 1,640.0 MW | withdrawn | Louisiana |
| MISO Queue Project APP-100096 — Gas in an unlisted county, Louisiana | APP-100096 | Gas | 1,640.0 MW | withdrawn | Louisiana |
| Richland Parish generators | E0044 | Gas | 1,640.0 MW | active | Richland Parish, Louisiana |
| Richland Parish generators | E0043 | Gas | 1,640.0 MW | active | Richland Parish, Louisiana |
| Franklin Farms | E0014 | Gas | 1,640.0 MW | active | Richland Parish, Louisiana |
| MISO Queue Project G867 — Nuclear in Monroe, Michigan | G867 | Nuclear | 1,563.0 MW | withdrawn | Monroe, Michigan |
| MISO Queue Project J4186 — Generation in an unlisted county, the U.S. | J4186 | — | 1,540.0 MW | withdrawn | — |
| Sugar Creek - Cayuga CT 345.0kV | J3999 | Gas | 1,540.0 MW | operational | Vermillion, Indiana |
| STERLINGTON 500 SWYD | J4022 | Gas | 1,509.0 MW | withdrawn | Ouachita, Louisiana |
| MISO Queue Project IP05 — Other in Randolph, Illinois | IP05 | Other | 1,500.0 MW | withdrawn | Randolph, Illinois |
| MISO Queue Project G902 — Wind in Winnebago, Illinois | G902 | Wind | 1,500.0 MW | withdrawn | Winnebago, Illinois |
| MISO Queue Project G898 — Wind in Benton, Minnesota | G898 | Wind | 1,500.0 MW | withdrawn | Benton, Minnesota |
| MISO Queue Project G882 — Wind in Dodge, Minnesota | G882 | Wind | 1,500.0 MW | withdrawn | Dodge, Minnesota |
| MISO Queue Project G883 — Wind in Olmsted, Minnesota | G883 | Wind | 1,500.0 MW | withdrawn | Olmsted, Minnesota |
| MISO Queue Project G704 — Wind in Hand, South Dakota | G704 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project G895 — Wind in Scott, Minnesota | G895 | Wind | 1,500.0 MW | withdrawn | Scott, Minnesota |
| MISO Queue Project J4220 — Generation in an unlisted county, the U.S. | J4220 | — | 1,500.0 MW | withdrawn | — |
| MISO Queue Project G884 — Wind in Roberts, South Dakota | G884 | Wind | 1,500.0 MW | withdrawn | Roberts, South Dakota |
| MISO Queue Project J4219 — Generation in an unlisted county, the U.S. | J4219 | — | 1,500.0 MW | operational | — |
| MISO Queue Project J4216 — Generation in an unlisted county, the U.S. | J4216 | — | 1,500.0 MW | operational | — |
| COLY | J4071 | Gas | 1,500.0 MW | withdrawn | Livingston, Louisiana |
| MISO Queue Project G896 — Wind in Scott, Minnesota | G896 | Wind | 1,500.0 MW | withdrawn | Scott, Minnesota |
| MISO Queue Project J4221 — Generation in an unlisted county, the U.S. | J4221 | — | 1,500.0 MW | operational | — |
| MISO Queue Project G703 — Wind in Hand, South Dakota | G703 | Wind | 1,500.0 MW | withdrawn | Hand, South Dakota |
| MISO Queue Project IP14 — Coal in Washington, Illinois | IP14 | Coal | 1,500.0 MW | operational | Washington, Illinois |
| MISO Queue Project G897 — Wind in Benton, Minnesota | G897 | Wind | 1,500.0 MW | withdrawn | Benton, Minnesota |
| Other_ | J4024 | Gas | 1,499.0 MW | operational | Monroe, Michigan |
| Other_ | J4025 | Gas | 1,499.0 MW | operational | Monroe, Michigan |
| BLACKFOOT - MADRID 345.0kV | J3799 | Gas | 1,452.0 MW | operational | Livingston, Michigan |
| HIPLE | J3922 | Gas | 1,445.0 MW | operational | Branch, Michigan |
| MISO Queue Project G265 — Other in Campbell, Wyoming | G265 | Other | 1,420.0 MW | withdrawn | Campbell, Wyoming |
| Majestic-Milan 345 kV Line | J3923 | Gas | 1,414.0 MW | operational | Washtenaw, Michigan |
| MISO Queue Project J372 — Nuclear in Rock Island, Illinois | J372 | Nuclear | 1,373.0 MW | withdrawn | Rock Island, Illinois |
| MISO Queue Project G051 — Coal in Milwaukee, Wisconsin | G051 | Coal | 1,300.0 MW | operational | Milwaukee, Wisconsin |
| DONALDSONVILLE - EVERGREEN 230.0kV | J4109 | Gas | 1,300.0 MW | withdrawn | Iberville, Louisiana |
| MISO Queue Project G484 — Coal in Switzerland, Indiana | G484 | Coal | 1,290.0 MW | withdrawn | Switzerland, Indiana |
| MISO Queue Project J433 — Gas in Union, Arkansas | J433 | Gas | 1,270.0 MW | withdrawn | Union, Arkansas |
| MISO Queue Project J376 — Gas in Union, Arkansas | J376 | Gas | 1,270.0 MW | operational | Union, Arkansas |
| Cayuga 345 kV Substation | J802 | Gas | 1,244.0 MW | withdrawn | Vermillion County, Indiana |
| MISO Queue Project J480 — Gas in Cherokee, Texas | J480 | Gas | 1,240.0 MW | withdrawn | Cherokee, Texas |
| MISO Queue Project J542 — Gas in Vigo, Indiana | J542 | Gas | 1,235.0 MW | withdrawn | Vigo, Indiana |
| MISO Queue Project G493 — Other in Van Buren, Michigan | G493 | Other | 1,221.0 MW | withdrawn | Van Buren, Michigan |
| MISO Queue Project E0016 — Gas in Calumet, Wisconsin | E0016 | Gas | 1,211.2 MW | active | Calumet, Wisconsin |
| Red Oak Ridge Energy Center | E0012 | Gas | 1,211.2 MW | active | Kenosha, Wisconsin |
| Other_ | J4165 | Gas | 1,203.0 MW | operational | Kenosha, Wisconsin |
| North Madison 345/138 kV | J4164 | Gas | 1,203.0 MW | operational | Dane, Wisconsin |
| MISO Queue Project G167 — Other in Kenosha, Wisconsin | G167 | Other | 1,200.0 MW | withdrawn | Kenosha, Wisconsin |
| MISO Queue Project G482 — Coal in Ashtabula, Ohio | G482 | Coal | 1,200.0 MW | withdrawn | Ashtabula, Ohio |
| MISO Queue Project J434 — Gas in Vermillion, Indiana | J434 | Gas | 1,185.0 MW | withdrawn | Vermillion, Indiana |
| MISO Queue Project J435 — Gas in Eau Claire, Wisconsin | J435 | Gas | 1,185.0 MW | withdrawn | Eau Claire, Wisconsin |
| Belle River - Fitz #2 345 kV Line Tap | J793 | Gas | 1,175.0 MW | operational | St. Clair County, Michigan |
| Sabine 138 & 230 kV (bus #334440, #334431, #334433 | R1003 | — | 1,166.0 MW | operational | Orange, — |
| Astoria 345kV substation | J3941 | Gas | 1,144.0 MW | operational | Deuel, South Dakota |
| Elm Road | R1053 | Gas | 1,138.0 MW | operational | Milwaukee, Wisconsin |
| Covert | J1848 | Gas | 1,128.0 MW | withdrawn | Van Buren, Michigan |
| Covert - Palisades 345kV Line | J812 | Gas | 1,108.0 MW | withdrawn | Van Buren County, Michigan |
| MISO Queue Project G259 — Gas in Dakota, Minnesota | G259 | Gas | 1,100.0 MW | withdrawn | Dakota, Minnesota |
| Malden CCGT | E0035 | Gas | 1,089.8 MW | active | Porter, Indiana |
| MISO Queue Project J404 — Gas in Jefferson Parish, Louisiana | J404 | Gas | 1,078.0 MW | withdrawn | Jefferson Parish, Louisiana |
| MISO Queue Project J259 — Gas in Shelby, Indiana | J259 | Gas | 1,065.0 MW | withdrawn | Shelby, Indiana |
| MISO Queue Project G260 — Gas in Goodhue, Minnesota | G260 | Gas | 1,061.0 MW | withdrawn | Goodhue, Minnesota |
| MISO Queue Project J484 — Gas in Calcasieu Parish, Louisiana | J484 | Gas | 1,056.2 MW | operational | Calcasieu Parish, Louisiana |
| MISO Queue Project G065 — Gas in St. Clair, Michigan | G065 | Gas | 1,050.0 MW | withdrawn | St. Clair, Michigan |
| MISO Queue Project J472 — Gas in Montgomery, Texas | J472 | Gas | 1,044.8 MW | operational | Montgomery, Texas |
| Cayuga Steam Station Switchyards 230kV and 345kV | R1044 | — | 1,040.0 MW | operational | Vermillion, — |
| Austin Substation 345kV Bus | J955 | Gas | 1,040.0 MW | operational | Sangamon County, Illinois |
| MISO Queue Project J396 — Gas in St. Charles Parish, Louisiana | J396 | Gas | 1,020.0 MW | operational | St. Charles Parish, Louisiana |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-27 | Colony - Plum Grove 230 kV | new_project | — | operational |
| 2026-08-27 | OAK GROVE - SUB 93 LOUISA 345.0kV | status | operational | withdrawn |
| 2026-08-27 | OAK GROVE - SUB 93 LOUISA 345.0kV | withdrawn_date | — | 2026-08-25 |
| 2026-08-27 | Cedar Mountain - Lyon County 345.0kV | proposed_online_date | 2028-09-30 | 2030-09-30 |
| 2026-08-27 | Cedar Mountain - Lyon County 345.0kV | operational_date | 2028-09-30 | 2030-09-30 |
| 2026-08-27 | Cedar Mountain - Lyon County 345.0kV | proposed_online_date | 2028-09-30 | 2030-09-30 |
| 2026-08-27 | Cedar Mountain - Lyon County 345.0kV | operational_date | 2028-09-30 | 2030-09-30 |
| 2026-08-26 | MISO Queue Project R5098 — Generation in an unlisted county, the U.S. | new_project | — | operational |
| 2026-08-26 | White Bluff EHV 500MW | new_project | — | operational |
| 2026-08-21 | MISO Queue Project J4256 — Generation in an unlisted county, the U.S. | new_project | — | operational |
| 2026-08-21 | MISO Queue Project J4255 — Generation in an unlisted county, the U.S. | new_project | — | operational |
| 2026-08-20 | MISO Queue Project J4254 — Generation in an unlisted county, the U.S. | new_project | — | operational |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through MISO.