Big Stone South 230kV Substation (J722)

Big Stone South 230kV Substation is a 200.0 MW wind interconnection project in Codington County,Deuel County, South Dakota with a current status of withdrawn. It is proposed to connect at Big Stone South 230kV Substation.

200.0 MWCapacity
WithdrawnStatus
—Market
WindTechnology

Project facts

Canonical nameBig Stone South 230kV Substation
Queue IDJ722
Statuswithdrawn
Source statusWithdrawn
Market—
TechnologyWind
Capacity200.0 MW
StateSouth Dakota
CountyCodington County,Deuel County
Point of interconnectionBig Stone South 230kV Substation
Requested (queue) date2017-06-16
Proposed in-service date2021-09-15
Operational date2021-09-15
Withdrawn date2026-08-28
Developer—
Utility / transmission ownerOtter Tail Power Company

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-05withdrawn_date—2026-08-28high
2026-09-05statusoperationalwithdrawnhigh
2026-07-29new_project—operationalhigh

Explore related data

Source last checked2026-10-12
Data last materially changed2026-10-12
Page data generated2026-10-12

Provenance: MISO — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata