BIO VERDE PV - KETTLEMAN 3 (596)

BIO VERDE PV - KETTLEMAN 3 is a 20.0 MW solar interconnection project in Kings, California with a current status of withdrawn. It is proposed to connect at Henrietta Tulare 70kV line.

20.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameBIO VERDE PV - KETTLEMAN 3
Queue ID596
Statuswithdrawn
Source statusWITHDRAWN
Market
TechnologySolar
Capacity20.0 MW
StateCalifornia
CountyKings
Point of interconnectionHenrietta Tulare 70kV line
Requested (queue) date2010-02-01
Proposed in-service date
Operational date
Withdrawn date2010-11-19
Developer
Utility / transmission ownerPGAE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: California ISO — public interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata