Biomass Project (191)

Biomass Project is a 26.0 MW other interconnection project in Litchfield, Connecticut with a current status of withdrawn. It is proposed to connect at CL&P 115 kV line #1238.

26.0 MWCapacity
WithdrawnStatus
SWCTMarket
OtherTechnology

Project facts

Canonical nameBiomass Project
Queue ID191
Statuswithdrawn
Source statusW
MarketSWCT
TechnologyOther
Capacity26.0 MW
StateConnecticut
CountyLitchfield
Point of interconnectionCL&P 115 kV line #1238
Requested (queue) date2006-12-22
Proposed in-service date2013-03-01
Operational date
Withdrawn date2010-09-13
Developer
Utility / transmission ownerISO-NE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-08-04new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-04
Data last materially changed2026-08-04
Page data generated2026-08-27

Provenance: isone-irtt. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata