Bismark 500kV (W4-037)

Bismark 500kV is a 32.0 MW battery interconnection project in Grant, West Virginia with a current status of withdrawn.

32.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameBismark 500kV
Queue IDW4-037
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity32.0 MW
StateWest Virginia
CountyGrant
Point of interconnection
Requested (queue) date2010-12-30
Proposed in-service date2018-12-31
Operational date
Withdrawn date2018-11-05
Developer
Utility / transmission ownerDominion

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata