Dominion is associated with 1,936 tracked interconnection projects representing 185,728 MW of requested capacity.
Entity resolution: this utility / transmission entity rolls up 7 source organization name(s) that were auto-matched into a single canonical cluster. Attribution is inferred from source records and may include related special-purpose entities.
1,936Projects
293Active
331Operational
1,305Withdrawn
185,728 MWRequested capacity
1Markets
Capacity by technology
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 1,143 | 84,459 MW |
| Gas | 195 | 39,048 MW |
| Battery | 412 | 31,134 MW |
| Wind | 34 | 13,168 MW |
| Other | 97 | 8,055 MW |
| Solar+Battery | 49 | 5,727 MW |
| Offshore Wind | 5 | 4,089 MW |
| Hydro | 1 | 48 MW |
Portfolio by market
| Market | Projects |
|---|---|
| PJM | 323 |
Geographic footprint
| State | Projects |
|---|---|
| Virginia | 1,475 |
| North Carolina | 250 |
| South Carolina | 176 |
| West Virginia | 15 |
| Georgia | 8 |
| Ohio | 3 |
| Connecticut | 2 |
| California | 1 |
Projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Coastal Virginia Offshore Wind (CVOW) Commercial Project | 64550_CVOWC | Wind | 2,640.0 MW | active | Virginia |
| Heritage-Carson | Z1-086 | Gas | 1,681.0 MW | operational | Greensville, Virginia |
| Chickahominy 500kV | AC1-107 | Gas | 1,600.0 MW | withdrawn | Charles City, Virginia |
| North Anna 500kV | Q65 | Other | 1,594.0 MW | withdrawn | Louisa, Virginia |
| Chesterfield 230kV | X2-082 | Gas | 1,575.0 MW | withdrawn | Chesterfield, Virginia |
| Brunswick 500kV | Y2-097 | Gas | 1,551.0 MW | withdrawn | Brunswick, Virginia |
| Carson-Wake 500kV | X2-076 | Gas | 1,525.5 MW | operational | Brunswick, Virginia |
| Millstone | 566_3 | Other | 1,350.0 MW | operational | New London, Connecticut |
| Gordonsville 230 kV | AH1-676 - moved to TC2 | Gas | 1,294.6 MW | withdrawn | Orange, Virginia |
| PJM Queue Project AH1-676 — Gas in Orange, Virginia | AH1-676 | Gas | 1,294.6 MW | withdrawn | Orange, Virginia |
| Mackeys 230 kV | AF1-236 | Solar | 1,210.0 MW | withdrawn | Tyrell, North Carolina |
| Southeast Queue Project 20180112001 — Gas in Anderson, South Carolina | 20180112001 | Gas | 1,200.0 MW | withdrawn | Anderson, South Carolina |
| Chickahominy 500kV | AB2-068 | Gas | 1,060.0 MW | withdrawn | Charles City, Virginia |
| V C Summer | 6127_1 | Other | 1,029.6 MW | operational | Fairfield, South Carolina |
| Four Rivers 500kV | T168 | Gas | 1,010.0 MW | withdrawn | Hanover, Virginia |
| Chesapeake 230 kV | AE2-007 | Gas | 967.6 MW | withdrawn | City Of Chesapeake, Virginia |
| Front Royal 500kV | V2-030 | Gas | 950.0 MW | operational | Warren, Virginia |
| Possum Point 230kV | V1-031 | Gas | 950.0 MW | withdrawn | Prince William, Virginia |
| Millstone | 566_2 | Other | 909.9 MW | operational | New London, Connecticut |
| Southeast Queue Project 20200910001 — Gas in Berkeley, South Carolina | 20200910001 | Gas | 870.0 MW | withdrawn | Berkeley, South Carolina |
| Chesapeake 230kV | AB2-051 | Gas | 840.0 MW | withdrawn | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-124 - moved to TC1 | Wind | 836.0 MW | operational | City Of Chesapeake, Virginia |
| CVOW 2, OSS 2 – T2G07 | AF1-124 | Offshore Wind | 836.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-123 - moved to TC1 | Wind | 833.0 MW | active | City Of Chesapeake, Virginia |
| CVOW 1, OSS 1 - T1L11 | AF1-123 | Offshore Wind | 833.0 MW | active | City Of Chesapeake, Virginia |
| Harper 230 kV | AF1-125 - moved to TC1 | Wind | 820.0 MW | operational | City Of Chesapeake, Virginia |
| CVOW 3, OSS 3 – T3G15 | AF1-125 | Offshore Wind | 820.0 MW | active | City Of Chesapeake, Virginia |
| Landstown 230 kV | AE2-124 - moved to TC1 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Virginia Beach 230 kV | AE1-067 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Birdneck-Landstown 230 kV | AE2-123 - moved to TC1 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| PJM Queue Project AE2-123 — Offshore Wind in City Of Virginia Beach, Virginia | AE2-123 | Offshore Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Virginia Beach 230 kV | AE1-065 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Virginia Beach 230 kV | AE1-066 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| PJM Queue Project AE2-124 — Offshore Wind in City Of Virginia Beach, Virginia | AE2-124 | Offshore Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Birdneck-Landstown 230 kV | AE2-122 | Wind | 800.1 MW | withdrawn | City Of Virginia Beach, Virginia |
| Carson-Suffolk 500 kV | AE1-173 | Solar | 800.0 MW | active | Sussex, Virginia |
| Pleasant View-Brambleton 230kV | X4-039 | Gas | 800.0 MW | operational | Loudoun, Virginia |
| PJM Queue Project AH1-712 — Gas in Fluvanna, Virginia | AH1-712 | Gas | 776.0 MW | active | Fluvanna, Virginia |
| Cunningham 500 kV | AH1-712 - moved to TC2 | Gas | 776.0 MW | active | Fluvanna, Virginia |
| Cunningham 500 kV | AH1-723 - moved to TC2 | Gas | 776.0 MW | active | Fluvanna, Virginia |
| PJM Queue Project AH1-723 — Gas in Fluvanna, Virginia | AH1-723 | Gas | 776.0 MW | active | Fluvanna, Virginia |
| Southeast Queue Project 20200910002 — Gas in Berkeley, South Carolina | 20200910002 | Gas | 720.0 MW | withdrawn | Berkeley, South Carolina |
| Gainesville 230kV | T180 | Gas | 690.0 MW | withdrawn | Prince William, Virginia |
| Brunswick-Wake 500 kV | AC2-093 | Solar | 675.0 MW | withdrawn | Northhampton, North Carolina |
| Bremo 230kV | P38 | Gas | 675.0 MW | operational | Buckingham, Virginia |
| PJM Queue Project AH1-716 — Battery in James City, Virginia | AH1-716 | Battery | 650.0 MW | active | James City, Virginia |
| Surry-Skiffes Creek 500kV | AH1-716 - moved to TC2 | Battery | 650.0 MW | active | James City, Virginia |
| Ladysmith CT 230kV | W1-073 | Gas | 612.0 MW | withdrawn | Caroline, Virginia |
| Remington CT 230kV | W1-074 | Gas | 610.0 MW | withdrawn | Fauquier, Virginia |
| Surry-Skiffes Creek 500kV | AH1-726 - moved to TC2 | Battery | 600.0 MW | withdrawn | James City, Virginia |
| Southeast Queue Project 20210901001 — Solar+Battery in Richland, South Carolina | 20210901001 | Solar+Battery | 600.0 MW | withdrawn | Richland, South Carolina |
| Bellflower Solar (VA) | 68071_BELLF | Solar | 600.0 MW | active | Brunswick, Virginia |
| PJM Queue Project AH1-726 — Battery in James City, Virginia | AH1-726 | Battery | 600.0 MW | withdrawn | James City, Virginia |
| Possum Point | P08 | Gas | 600.0 MW | withdrawn | Prince William, Virginia |
| Birchwood 230kV | T149 | Gas | 580.0 MW | withdrawn | King George, Virginia |
| Chesterfield 230 kV | AF1-128 - moved to TC1 | Gas | 569.0 MW | active | Chesterfield, Virginia |
| Chesterfield CT Units 1 and 2 | AF1-128 | Gas | 569.0 MW | active | Chesterfield, Virginia |
| Chesterfield 230 kV | AF1-129 | Gas | 569.0 MW | active | Chesterfield, Virginia |
| Midlothian 230kV | U3-016 | Gas | 550.0 MW | withdrawn | Goochland, Virginia |
| Loudoun-Meadowbrook 500kV | X3-076 | Gas | 510.0 MW | withdrawn | Fauquier, Virginia |
| PJM Queue Project AG1-178 — Solar in Sussex, Virginia | AG1-178 | Solar | 500.0 MW | withdrawn | Sussex, Virginia |
| Carson-Rogers Rd 500 kV | AE1-068 | Solar | 500.0 MW | withdrawn | Greensville, Virginia |
| PJM Queue Project AG2-655 — Solar in Grant, West Virginia | AG2-655 | Solar | 500.0 MW | withdrawn | Grant, West Virginia |
| Randolph Solar | AF2-042 | Solar | 500.0 MW | active | Halifax, Virginia |
| Chickahominy - Surry 500 kV | AG2-475 | Battery | 500.0 MW | withdrawn | Charles City, Virginia |
| Mt. Storm-Bismark 500 kV | AG2-655 - moved to TC2 | Solar | 500.0 MW | withdrawn | Grant, West Virginia |
| Carson-Rodgers Road 500 kV | AD2-197 | Solar | 500.0 MW | withdrawn | Greensville, Virginia |
| Clover-Rawlings 500 kV | AF2-042 - moved to TC1 | Solar | 500.0 MW | active | Halifax, Virginia |
| Carson-Suffolk 500 kV | AG1-178 - moved to TC1 | Solar | 500.0 MW | withdrawn | Sussex, Virginia |
| Pendleton 230 kV | W3-043 | Wind | 500.0 MW | withdrawn | City Of Virginia Beach, Virginia |
| Spotsylvania 500kV | AC1-158 | Solar | 485.0 MW | operational | Spotsylvania, Virginia |
| Front Royal 500kV | V4-018 | Gas | 475.0 MW | operational | Warren, Virginia |
| Southeast Queue Project 20220118001 — Solar+Battery in Richland, South Carolina | 20220118001 | Solar+Battery | 450.0 MW | withdrawn | Richland, South Carolina |
| Surry - Yadkin 500 kV | AH1-645 | Solar | 450.0 MW | withdrawn | Isle Of Wight, Virginia |
| Jasper | 55927_ST1 | Gas | 443.7 MW | operational | Jasper, South Carolina |
| Brambleton-Goose Creek 500kV | AH1-727 - moved to TC2 | Battery | 425.0 MW | active | Loudoun, Virginia |
| PJM Queue Project AH1-727 — Battery in Loudoun, Virginia | AH1-727 | Battery | 425.0 MW | active | Loudoun, Virginia |
| Cope | 7210_ST1 | Gas | 417.3 MW | operational | Orangeburg, South Carolina |
| Monarch I Interconnection 500 kV | AG2-437 | Solar | 400.0 MW | withdrawn | Greensville, Virginia |
| Southeast Queue Project 20220601002 — Solar+Battery in Richland, South Carolina | 20220601002 | Solar+Battery | 400.0 MW | withdrawn | Richland, South Carolina |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-08-14 | Harper 230 kV | status | active | operational |
| 2026-08-14 | Harper 230 kV | operational_date | — | 2032-12-31 |
| 2026-08-14 | Harper 230 kV | proposed_online_date | 2032-12-31 | — |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-08-27
Page data generated2026-08-27
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.
Track queue activity connecting through Dominion.
Start tracking with interXdata