Blackland Prairie 3 Energy Storage (27INR0487)

Blackland Prairie 3 Energy Storage is a 102.1 MW other interconnection project in Travis, Texas with a current status of operational. It is proposed to connect at 9328 Austrop 138kV.

102.1 MWCapacity
OperationalStatus
TravisMarket
OtherTechnology

Project facts

Canonical nameBlackland Prairie 3 Energy Storage
Queue ID27INR0487
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketTravis
TechnologyOther
Capacity102.1 MW
StateTexas
CountyTravis
Point of interconnection9328 Austrop 138kV
Requested (queue) date2025-03-24
Proposed in-service date
Operational date2027-12-01
Withdrawn date
DeveloperBalcones Ridge Resiliency III LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-28

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.