Blain 115 kV II is a 12.0 MW battery interconnection project in Perry, Pennsylvania with a current status of withdrawn.

12.0 MWCapacity
WithdrawnStatus
Market
BatteryTechnology

Project facts

Canonical nameBlain 115 kV II
Queue IDAF1-295
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyBattery
Capacity12.0 MW
StatePennsylvania
CountyPerry
Point of interconnection
Requested (queue) date2019-09-30
Proposed in-service date2022-12-31
Operational date
Withdrawn date2020-03-25
Developer
Utility / transmission ownerPENELEC

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.