Blue Energy Center - Port of Victoria Phase 1b – CCGT (29INR0248)

Blue Energy Center - Port of Victoria Phase 1b – CCGT is a 1,110.0 MW gas interconnection project in Victoria, Texas with a current status of operational. It is proposed to connect at Tap <345kV> <#80286> <DULCE7A> - <#8676> <STATIC7A>.

1,110.0 MWCapacity
OperationalStatus
VictoriaMarket
GasTechnology

Project facts

Canonical nameBlue Energy Center - Port of Victoria Phase 1b – CCGT
Queue ID29INR0248
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketVictoria
TechnologyGas
Capacity1,110.0 MW
StateTexas
CountyVictoria
Point of interconnectionTap <345kV> <#80286> <DULCE7A> - <#8676> <STATIC7A>
Requested (queue) date2026-01-26
Proposed in-service date—
Operational date2031-10-17
Withdrawn date—
DeveloperBrother 1, LLC
Utility / transmission ownerERCOT

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-30capacity_mw1264.61110high
2026-07-31new_project—operationalhigh

Explore related data

Source last checked2026-09-30
Data last materially changed2026-09-30
Page data generated2026-10-11

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata