Blue River 138kV (GEN-2016-102)

Blue River 138kV is a 147.5 MW wind interconnection project in Pontotoc, Oklahoma with a current status of operational. It is proposed to connect at Blue River 138kV.

147.5 MWCapacity
OperationalStatus
OKMarket
WindTechnology

Project facts

Canonical nameBlue River 138kV
Queue IDGEN-2016-102
Statusoperational
Source statusIA FULLY EXECUTED/COMMERCIAL OPERATION
MarketOK
TechnologyWind
Capacity147.5 MW
StateOklahoma
CountyPontotoc
Point of interconnectionBlue River 138kV
Requested (queue) date2016-11-07
Proposed in-service date—
Operational date2023-11-01
Withdrawn date—
Developer—
Utility / transmission ownerOGE

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-09-04statusactiveoperationalhigh
2026-09-04proposed_online_date2025-12-19—medium
2026-09-04operational_date—2023-11-01medium
2026-07-31new_project—activehigh

Explore related data

Source last checked2026-11-26
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: Southwest Power Pool — generator interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata