Bluebonnet Trail Solar (27INR0417)

Bluebonnet Trail Solar is a 150.9 MW solar interconnection project in Ellis, Texas with a current status of operational. It is proposed to connect at Tap 345 kV (#2427) WATMLL_W5 - (#2466) BIGONION_5 .

150.9 MWCapacity
OperationalStatus
EllisMarket
SolarTechnology

Project facts

Canonical nameBluebonnet Trail Solar
Queue ID27INR0417
Statusoperational
Source statusSS Completed, FIS Started, No IA
MarketEllis
TechnologySolar
Capacity150.9 MW
StateTexas
CountyEllis
Point of interconnectionTap 345 kV (#2427) WATMLL_W5 - (#2466) BIGONION_5
Requested (queue) date2024-12-19
Proposed in-service date
Operational date2028-09-19
Withdrawn date
DeveloperBluebonnet trail solar LLC
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata