Bluestone Battery Storage (0741)

Bluestone Battery Storage is a 10.0 MW battery interconnection project in Broome, New York with a current status of withdrawn. It is proposed to connect at Afton - Stilesville 115kV.

10.0 MWCapacity
WithdrawnStatus
EMarket
BatteryTechnology

Project facts

Canonical nameBluestone Battery Storage
Queue ID0741
Statuswithdrawn
Source status0
MarketE
TechnologyBattery
Capacity10.0 MW
StateNew York
CountyBroome
Point of interconnectionAfton - Stilesville 115kV
Requested (queue) date2018-07-02
Proposed in-service date2020-04-30
Operational date
Withdrawn date
DeveloperBluestone Wind, LLC
Utility / transmission ownerNYSEG

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: New York ISO — interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata