BlueWater Solar (2292)

BlueWater Solar is a 1,016.4 MW solar+battery interconnection project in La Paz, Arizona with a current status of withdrawn. It is proposed to connect at Cielo Azul.

1,016.4 MWCapacity
WithdrawnStatus
CAISOMarket
Solar+BatteryTechnology

Project facts

Canonical nameBlueWater Solar
Queue ID2292
Statuswithdrawn
Source statuswithdrawn
MarketCAISO
TechnologySolar+Battery
Capacity1,016.4 MW
StateArizona
CountyLa Paz
Point of interconnectionCielo Azul
Requested (queue) date2023-04-17
Proposed in-service date2028-12-29
Operational date
Withdrawn date2025-05-27
Developer
Utility / transmission ownerDCRT

What changed

No material field-level changes have been recorded for this project since the baseline snapshot. interXdata detects changes as new source snapshots are ingested and diffed against prior state.

Explore related data

Source last checked2026-07-31
Data last materially changed2026-07-31
Page data generated2026-08-27

Provenance: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata