Bluff Point-Jay 138kV is a 75.0 MW wind interconnection project in Jay, Indiana with a current status of withdrawn.

75.0 MWCapacity
WithdrawnStatus
Market
WindTechnology

Project facts

Canonical nameBluff Point-Jay 138kV
Queue IDS26
Statuswithdrawn
Source statusWithdrawn
Market
TechnologyWind
Capacity75.0 MW
StateIndiana
CountyJay
Point of interconnection
Requested (queue) date2007-04-09
Proposed in-service date2009-01-01
Operational date
Withdrawn date2008-05-29
Developer
Utility / transmission ownerAEP

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.