Indiana Interconnection Projects

interXdata tracks 1,548 interconnection projects in Indiana representing 236,733 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are White, Randolph, Sullivan.

1,548Total projects
128Active
626Operational
779Withdrawn
236,733 MWRequested capacity
25,465 MWActive capacity

Technology mix

TechnologyProjectsRequested capacity
Solar70090,036 MW
Gas25244,502 MW
Wind20841,075 MW
Battery22526,595 MW
Other13823,360 MW
Solar+Battery137,000 MW
Coal93,547 MW
Gas+Battery1530 MW
Hydro288 MW

Counties

CountyProjectsRequested capacity
White9713,311 MW
Randolph505,149 MW
Sullivan4915,942 MW
Vermillion4612,721 MW
Marion452,369 MW
St. Joseph396,030 MW
Jay382,587 MW
St Joseph371,012 MW
Benton356,359 MW
Madison322,838 MW
Pulaski315,151 MW
Vigo297,395 MW
LaPorte282,926 MW
Lake284,347 MW
Delaware272,038 MW
Allen262,300 MW
Knox264,523 MW
Montgomery253,232 MW
Jasper257,126 MW
Elkhart25873 MW
Pike244,581 MW
Marshall243,373 MW
Henry242,254 MW
Fountain244,456 MW
Blackford232,680 MW
Hendricks22456 MW
Tippecanoe20858 MW
Clinton193,637 MW
Grant191,032 MW
Wayne18753 MW
Posey162,836 MW
Porter162,926 MW
Gibson165,026 MW
Greene162,128 MW
Decatur162,578 MW
Spencer168,008 MW
Starke152,491 MW
Newton152,481 MW
Lawrence152,709 MW
Huntington142,202 MW

Largest projects

ProjectQueue IDTechnologyCapacityStatusLocation
Schahfer CCGTsE0042Gas2,739.8 MWactiveJasper, Indiana
MISO Queue Project J236 — Wind in White, IndianaJ236Wind2,400.0 MWwithdrawnWhite, Indiana
Sugar Creek - Cayuga CT 345.0kVJ3999Gas1,540.0 MWoperationalVermillion, Indiana
Dumont-Greentown 765kVX1-020Wind1,500.0 MWwithdrawnCass, Indiana
IN Queue Project LGE-GIS-2022-005 — Solar+Battery in Clarke And Jefferson Counties, Indiana, IndianaLGE-GIS-2022-005Solar+Battery1,400.0 MWwithdrawnClarke And Jefferson Counties, Indiana, Indiana
IN Queue Project LGE-GIS-2022-006 — Solar+Battery in Clarke And Jefferson Counties, Indiana, IndianaLGE-GIS-2022-006Solar+Battery1,400.0 MWwithdrawnClarke And Jefferson Counties, Indiana, Indiana
Rockport6166_2Other1,300.0 MWoperationalSpencer, Indiana
Rockport6166_1Other1,300.0 MWoperationalSpencer, Indiana
MISO Queue Project G484 — Coal in Switzerland, IndianaG484Coal1,290.0 MWwithdrawnSwitzerland, Indiana
Cayuga 345 kV SubstationJ802Gas1,244.0 MWwithdrawnVermillion County, Indiana
MISO Queue Project J542 — Gas in Vigo, IndianaJ542Gas1,235.0 MWwithdrawnVigo, Indiana
IN Queue Project LGE-GIS-2021-008 — Solar+Battery in Clark, IndianaLGE-GIS-2021-008Solar+Battery1,200.0 MWsuspendedClark, Indiana
MISO Queue Project J434 — Gas in Vermillion, IndianaJ434Gas1,185.0 MWwithdrawnVermillion, Indiana
State Line 138kVY3-063Gas1,161.0 MWwithdrawnLake, Indiana
Malden CCGTE0035Gas1,089.8 MWactivePorter, Indiana
MISO Queue Project J259 — Gas in Shelby, IndianaJ259Gas1,065.0 MWwithdrawnShelby, Indiana
Sullivan 345 kVAF1-088 - moved to TC1Other1,000.0 MWwithdrawnSullivan, Indiana
Sullivan 345 kVAF2-008 - moved to TC1Other1,000.0 MWwithdrawnSullivan, Indiana
Southeast Queue Project LGE-GIS-2022-006 — Solar+Battery in Clarke, IndianaLGE-GIS-2022-006Solar+Battery1,000.0 MWwithdrawnClarke, Indiana
MISO Queue Project J250 — Gas in Shelby, IndianaJ250Gas999.0 MWwithdrawnShelby, Indiana
Sycamore Riverside Energy, LLC70359_SYRVSGas964.0 MWactiveSullivan, Indiana
MISO Queue Project G011 — Gas in Pike, IndianaG011Gas900.0 MWwithdrawnPike, Indiana
AB Brown 138 kV subJ708Gas847.0 MWwithdrawnPosey County, Indiana
MISO Queue Project G015 — Gas in Lawrence, IndianaG015Gas800.0 MWwithdrawnLawrence, Indiana
PJM Queue Project AE2-130 — Solar+Battery in Spencer, IndianaAE2-130Solar+Battery800.0 MWwithdrawnSpencer, Indiana
Rockport 765 kVAE2-130 - moved to TC1Solar800.0 MWwithdrawnSpencer, Indiana
Rockport 765 kVAF2-353Solar800.0 MWwithdrawnSpencer, Indiana
Rockport 765 kVAE1-214Solar800.0 MWwithdrawnSpencer, Indiana
PJM Queue Project AH1-745 — Gas in Vermillion, IndianaAH1-745Gas770.0 MWwithdrawnVermillion, Indiana
PJM Queue Project AH1-740 — Gas in Vermillion, IndianaAH1-740Gas770.0 MWwithdrawnVermillion, Indiana

Top developers in Indiana

Recent material changes

ObservedProjectFieldOldNew
2026-11-21Bluff Point-Randolph 138 kVproposed_online_date2026-05-312028-07-31
2026-11-10Keystone-Desoto 345 kVoperational_date—2026-09-15
2026-11-10Keystone-Desoto 345 kVproposed_online_date2026-09-15—
2026-11-10Keystone-Desoto 345 kVstatusactiveoperational
2026-11-07Liberty Center-Buckeye Tap 69 kVwithdrawn_date2026-11-022026-11-06
2026-11-06Olive-Reynolds 345 kVproposed_online_date2022-12-312029-09-30
2026-11-05Sandborn Primary - Worthington Primary 161.0kVwithdrawn_date—2026-10-20
2026-11-05Sandborn Primary - Worthington Primary 161.0kVstatusoperationalwithdrawn
2026-11-05Frankfort - New London 230.0kVwithdrawn_date—2026-10-20
2026-11-05Frankfort - New London 230.0kVstatusoperationalwithdrawn
2026-11-05South Valparaiso 138 kV Substationwithdrawn_date—2026-10-20
2026-11-05South Valparaiso 138 kV Substationstatusoperationalwithdrawn

Explore related data

Source last checked2026-07-31
Data last materially changed2026-11-26
Page data generated2026-11-26

Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; lgeku-oasis; MISO — generator interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Get notified when a new project appears in Indiana.

Start tracking with interXdata