Indiana Interconnection Projects
interXdata tracks 1,564 interconnection projects in Indiana representing 240,153 MW of requested capacity. The dominant technology by capacity is Solar. The most active counties are White, Sullivan, Randolph.
1,564Total projects
133Active
658Operational
758Withdrawn
240,153 MWRequested capacity
26,450 MWActive capacity
Technology mix
| Technology | Projects | Requested capacity |
|---|---|---|
| Solar | 710 | 92,006 MW |
| Gas | 253 | 45,002 MW |
| Wind | 210 | 41,575 MW |
| Battery | 228 | 27,045 MW |
| Other | 138 | 23,359 MW |
| Solar+Battery | 13 | 7,000 MW |
| Coal | 9 | 3,547 MW |
| Gas+Battery | 1 | 530 MW |
| Hydro | 2 | 88 MW |
Counties
| County | Projects | Requested capacity |
|---|---|---|
| White | 97 | 13,311 MW |
| Sullivan | 56 | 17,642 MW |
| Randolph | 50 | 5,149 MW |
| Vermillion | 46 | 12,721 MW |
| Marion | 45 | 2,369 MW |
| St. Joseph | 39 | 6,030 MW |
| Jay | 38 | 2,587 MW |
| St Joseph | 37 | 1,012 MW |
| Benton | 35 | 6,359 MW |
| Madison | 32 | 2,838 MW |
| Pulaski | 31 | 5,151 MW |
| Vigo | 29 | 7,395 MW |
| Lake | 29 | 4,547 MW |
| LaPorte | 28 | 2,926 MW |
| Knox | 28 | 4,873 MW |
| Delaware | 27 | 2,038 MW |
| Allen | 26 | 2,300 MW |
| Montgomery | 25 | 3,232 MW |
| Elkhart | 25 | 873 MW |
| Jasper | 25 | 7,126 MW |
| Fountain | 24 | 4,456 MW |
| Pike | 24 | 4,581 MW |
| Marshall | 24 | 3,373 MW |
| Henry | 24 | 2,254 MW |
| Blackford | 23 | 2,680 MW |
| Hendricks | 22 | 456 MW |
| Tippecanoe | 21 | 1,058 MW |
| Grant | 19 | 1,032 MW |
| Clinton | 19 | 3,637 MW |
| Wayne | 18 | 753 MW |
| Greene | 17 | 2,348 MW |
| Spencer | 17 | 8,208 MW |
| Decatur | 16 | 2,578 MW |
| Posey | 16 | 2,836 MW |
| Gibson | 16 | 5,026 MW |
| Porter | 16 | 2,926 MW |
| Newton | 15 | 2,481 MW |
| Lawrence | 15 | 2,709 MW |
| Starke | 15 | 2,491 MW |
| Wells | 14 | 1,628 MW |
Largest projects
| Project | Queue ID | Technology | Capacity | Status | Location |
|---|---|---|---|---|---|
| Schahfer CCGTs | E0042 | Gas | 2,739.8 MW | active | Jasper, Indiana |
| MISO Queue Project J236 — Wind in White, Indiana | J236 | Wind | 2,400.0 MW | withdrawn | White, Indiana |
| Sugar Creek - Cayuga CT 345.0kV | J3999 | Gas | 1,540.0 MW | operational | Vermillion, Indiana |
| Dumont-Greentown 765kV | X1-020 | Wind | 1,500.0 MW | withdrawn | Cass, Indiana |
| IN Queue Project LGE-GIS-2022-006 — Solar+Battery in Clarke And Jefferson Counties, Indiana, Indiana | LGE-GIS-2022-006 | Solar+Battery | 1,400.0 MW | withdrawn | Clarke And Jefferson Counties, Indiana, Indiana |
| IN Queue Project LGE-GIS-2022-005 — Solar+Battery in Clarke And Jefferson Counties, Indiana, Indiana | LGE-GIS-2022-005 | Solar+Battery | 1,400.0 MW | withdrawn | Clarke And Jefferson Counties, Indiana, Indiana |
| Rockport | 6166_2 | Other | 1,300.0 MW | operational | Spencer, Indiana |
| Rockport | 6166_1 | Other | 1,300.0 MW | operational | Spencer, Indiana |
| MISO Queue Project G484 — Coal in Switzerland, Indiana | G484 | Coal | 1,290.0 MW | withdrawn | Switzerland, Indiana |
| Cayuga 345 kV Substation | J802 | Gas | 1,244.0 MW | withdrawn | Vermillion County, Indiana |
| MISO Queue Project J542 — Gas in Vigo, Indiana | J542 | Gas | 1,235.0 MW | withdrawn | Vigo, Indiana |
| IN Queue Project LGE-GIS-2021-008 — Solar+Battery in Clark, Indiana | LGE-GIS-2021-008 | Solar+Battery | 1,200.0 MW | suspended | Clark, Indiana |
| MISO Queue Project J434 — Gas in Vermillion, Indiana | J434 | Gas | 1,185.0 MW | withdrawn | Vermillion, Indiana |
| State Line 138kV | Y3-063 | Gas | 1,161.0 MW | withdrawn | Lake, Indiana |
| Malden CCGT | E0035 | Gas | 1,089.8 MW | active | Porter, Indiana |
| MISO Queue Project J259 — Gas in Shelby, Indiana | J259 | Gas | 1,065.0 MW | withdrawn | Shelby, Indiana |
| Sullivan 345 kV | AF1-088 - moved to TC1 | Other | 1,000.0 MW | withdrawn | Sullivan, Indiana |
| Southeast Queue Project LGE-GIS-2022-006 — Solar+Battery in Clarke, Indiana | LGE-GIS-2022-006 | Solar+Battery | 1,000.0 MW | withdrawn | Clarke, Indiana |
| Sullivan 345 kV | AF2-008 - moved to TC1 | Other | 1,000.0 MW | withdrawn | Sullivan, Indiana |
| MISO Queue Project J250 — Gas in Shelby, Indiana | J250 | Gas | 999.0 MW | withdrawn | Shelby, Indiana |
| Sycamore Riverside Energy, LLC | 70359_SYRVS | Gas | 964.0 MW | active | Sullivan, Indiana |
| MISO Queue Project G011 — Gas in Pike, Indiana | G011 | Gas | 900.0 MW | withdrawn | Pike, Indiana |
| AB Brown 138 kV sub | J708 | Gas | 847.0 MW | withdrawn | Posey County, Indiana |
| Rockport 765 kV | AE1-214 | Solar | 800.0 MW | withdrawn | Spencer, Indiana |
| Rockport 765 kV | AE2-130 - moved to TC1 | Solar | 800.0 MW | withdrawn | Spencer, Indiana |
| PJM Queue Project AE2-130 — Solar+Battery in Spencer, Indiana | AE2-130 | Solar+Battery | 800.0 MW | withdrawn | Spencer, Indiana |
| MISO Queue Project G015 — Gas in Lawrence, Indiana | G015 | Gas | 800.0 MW | withdrawn | Lawrence, Indiana |
| Rockport 765 kV | AF2-353 | Solar | 800.0 MW | withdrawn | Spencer, Indiana |
| PJM Queue Project AH1-745 — Gas in Vermillion, Indiana | AH1-745 | Gas | 770.0 MW | withdrawn | Vermillion, Indiana |
| PJM Queue Project AH1-740 — Gas in Vermillion, Indiana | AH1-740 | Gas | 770.0 MW | withdrawn | Vermillion, Indiana |
Top developers in Indiana
| Developer (canonical) | Projects | Capacity |
|---|---|---|
| RWE Solar Development, LLC | 5 | 480 MW |
| PJM Solar Devco I, LLC | 4 | 1,200 MW |
| Dolphin Solar LLC | 4 | 850 MW |
| Royerton Solar, LLC | 4 | 180 MW |
| NIPSCO | 4 | 4,987 MW |
| Wahoo Solar LLC | 4 | 800 MW |
| Dumont Solar, LLC | 4 | 260 MW |
| ACE Development Company, LLC | 3 | 335 MW |
| Invenergy | 3 | 310 MW |
| Leeward Renewable Energy Development, LLC | 3 | 430 MW |
| Cobia Solar LLC | 3 | 800 MW |
| Black Prairie Storage II LLC | 2 | 100 MW |
| ibV Energy Partners LLC | 2 | 190 MW |
| Prairie Creek Wind Farm II, LLC | 2 | 300 MW |
| Headwaters Wind Farm III LLC d/b/a Esker Solar Park LLC and Esker Solar Park II LLC | 2 | 240 MW |
Recent material changes
| Observed | Project | Field | Old | New |
|---|---|---|---|---|
| 2026-10-10 | Jay-Desoto 138 kV | withdrawn_date | — | 2026-10-09 |
| 2026-10-08 | Desoto 345 kV | proposed_online_date | 2026-05-31 | 2027-05-31 |
| 2026-10-08 | Desoto 345 kV | proposed_online_date | 2026-05-31 | 2027-05-31 |
| 2026-10-08 | Edwardsport IGCC - Amo 345.0kV | withdrawn_date | — | 2026-10-20 |
| 2026-10-08 | Edwardsport IGCC - Amo 345.0kV | status | operational | withdrawn |
| 2026-10-08 | Edwardsport IGCC - Amo 345.0kV | status | operational | withdrawn |
| 2026-10-08 | Edwardsport IGCC - Amo 345.0kV | withdrawn_date | — | 2026-10-06 |
| 2026-10-02 | Mammoth Central Solar Project | proposed_online_date | 2026-10-01 | 2026-11-01 |
| 2026-10-02 | Mammoth South Solar Project | proposed_online_date | 2026-09-01 | 2026-10-01 |
| 2026-10-02 | Bos Dairy, LLC | operational_date | — | 2026-08-01 |
| 2026-10-02 | Bos Dairy, LLC | proposed_online_date | 2026-08-01 | — |
| 2026-10-02 | Bos Dairy, LLC | status | active | operational |
Explore related data
Source last checked2026-07-31
Data last materially changed2026-10-11
Page data generated2026-10-11
Provenance: U.S. EIA — Form EIA-860M generator inventory (operating + planned); Lawrence Berkeley National Laboratory — Queued Up interconnection dataset; lgeku-oasis; MISO — generator interconnection queue; PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.