Boling Generation (TEF-Due Diligience) (24INR0576)
Boling Generation (TEF-Due Diligience) is a 400.0 MW gas interconnection project in Wharton, Texas with a current status of operational. It is proposed to connect at 43340 Gulftie 138kV.
400.0 MWCapacity
OperationalStatus
WhartonMarket
GasTechnology
Project facts
| Canonical name | Boling Generation (TEF-Due Diligience) |
|---|---|
| Queue ID | 24INR0576 |
| Status | operational |
| Source status | SS Completed, FIS Completed, No IA |
| Market | Wharton |
| Technology | Gas |
| Capacity | 400.0 MW |
| State | Texas |
| County | Wharton |
| Point of interconnection | 43340 Gulftie 138kV |
| Requested (queue) date | 2023-12-04 |
| Proposed in-service date | — |
| Operational date | 2028-12-16 |
| Withdrawn date | — |
| Developer | Boling Generation |
| Utility / transmission owner | ERCOT |
Cross-source records
This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.
What changed
| Observed | Field | Old value | New value | Materiality |
|---|---|---|---|---|
| 2026-07-31 | new_project | — | operational | high |
Explore related data
Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27
Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.