Boling Generation (TEF-Due Diligience) (24INR0576)

Boling Generation (TEF-Due Diligience) is a 400.0 MW gas interconnection project in Wharton, Texas with a current status of operational. It is proposed to connect at 43340 Gulftie 138kV.

400.0 MWCapacity
OperationalStatus
WhartonMarket
GasTechnology

Project facts

Canonical nameBoling Generation (TEF-Due Diligience)
Queue ID24INR0576
Statusoperational
Source statusSS Completed, FIS Completed, No IA
MarketWharton
TechnologyGas
Capacity400.0 MW
StateTexas
CountyWharton
Point of interconnection43340 Gulftie 138kV
Requested (queue) date2023-12-04
Proposed in-service date
Operational date2028-12-16
Withdrawn date
DeveloperBoling Generation
Utility / transmission ownerERCOT

Cross-source records

This project is also observed in: Lawrence Berkeley National Laboratory — Queued Up interconnection dataset. interXdata links these source records without double-counting the project.

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-31new_projectoperationalhigh

Explore related data

Source last checked2026-08-01
Data last materially changed2026-08-01
Page data generated2026-08-27

Provenance: ERCOT — Generation Interconnection Status (GIS) report. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.

Follow this project and get an alert when its status, capacity, developer, or schedule changes.

Start tracking with interXdata