Bon Ayr 69 kV (AG1-070 - moved to TC1)

Bon Ayr 69 kV is a 45.0 MW solar interconnection project in Barren, Kentucky with a current status of withdrawn.

45.0 MWCapacity
WithdrawnStatus
Market
SolarTechnology

Project facts

Canonical nameBon Ayr 69 kV
Queue IDAG1-070 - moved to TC1
Statuswithdrawn
Source statusWithdrawn
Market
TechnologySolar
Capacity45.0 MW
StateKentucky
CountyBarren
Point of interconnection
Requested (queue) date2020-07-30
Proposed in-service date2024-06-01
Operational date
Withdrawn date2025-11-03
Developer
Utility / transmission ownerEKPC

What changed

ObservedFieldOld valueNew valueMateriality
2026-07-29new_projectwithdrawnhigh

Explore related data

Source last checked2026-08-27
Data last materially changed2026-08-27
Page data generated2026-08-27

Provenance: PJM — new-services interconnection queue. Values are normalized from public source records into the interXdata canonical warehouse; see each source for original filings.